|
Best of 2005 Awards
Victory Bridge
Award of Merit: Bridges
Replacing a 75-year-old bridge poses enough of a task for
most contractors. But the team that built the new Victory
Bridge in New Jersey faced extra hurdles.
"The biggest challenge was taking over from the existing
contractor," one judge said, referring to how George
Harms Construction of Howell, N.J., won a bid to become the
general contractor after the New Jersey Department of Transportation
terminated its original design-build contract with Schiavone
Construction of Secaucus, N.J., over design criteria conflicts.
The $109 million project involved replacing Victory Bridge
- which connects Perth Amboy and Sayreville across the Raritan
River - with two new spans. Completed in September, eight
months ahead of schedule, the new bridge is, like its predecessor,
dedicated to New Jersey residents who served in World War
I.
The project team worked in stages because the centerline
of one of the new spans was only yards away from the centerline
of the original bridge, which remained in use during construction.
"It's only 30 ft. from the old bridge," one judge
said. "They had to keep that bridge operational."
The team built the new structure for southbound traffic first.
In June 2004, it shifted all four lanes of traffic from the
original bridge onto the new 3,971-ft.-long span. The team
then demolished the original bridge in order to build a second
3,971-ft. span for northbound lanes, only inches away from
the first.
The two new structures are connected with a cap to give a
unified appearance. Northbound traffic moved onto the second
span in September.
Each span of the new bridge has two 12-ft. lanes, 10-ft.
outside shoulders, and 3-ft. inside shoulders. The southbound
bridge has a 6-ft. sidewalk for pedestrians.
One of the team's main accomplishments was completing the
work on a compressed schedule through time-saving measures.
It shaved off months by including construction drawings -
and other information such as rebar bends, segment geometry,
and tendon stressing - in contractor bid documents.
Meanwhile, for the more complex pier, expansion joint, and
deviation segments, the team provided electronic files of
three-dimensional integrated color drawings to the steel contractor
in order to facilitate the fabrication process. The strategy
only required shop drawings for the expansion joints, bearings,
and post-tensioning hardware.
The new structure is New Jersey's first concrete segmental
bridge. The department of transportation selected this technology
for the foundation and deck for its speed of erection, low
life-cycle costs, and aesthetic appeal.
The concrete segments were cast in Virginia and barged to
the site for erection. Typical precast concrete segments are
9 ft., 4 in. long - a size selected to maximize ease of transportation
and erection. The pier segments were cast in halves, each
weighing 115 tons.
The fabricator constructed the 22 piers from precast concrete
hollow box sections that it connected with post-tensioning
techniques. The team was able to erect concrete piers as tall
as 100 ft. in one day.
The team built the main span deck using the balanced cantilever
construction method, which has superstructure erection begin
at the pier and progress outward in both directions. The team
erected the main span units and approach spans at the same
time to expedite the construction schedule. The two concrete
abutments were cast in place.
The new bridge slopes upward to a 355-ft. clearance - instead
of the old structure's 128-ft. height, which required a swing-span
that opened about 1,500 times a year for river traffic.
Each new span has a 440-ft.-long main center section and
two 330-ft.-long secondary sections on either side of the
center segment. In addition, the team erected 20 approach
spans - varying in length from 142 to 150 ft. - that connect
to the secondary spans.
"From my perspective, it's really quite elegant,"
said one judge.
Key Players
Owner: New Jersey Department
of Transportation
General Contractor: George
Harms Construction
Engineer of Record: FIGG
Precaster: Bayshore
Concrete Products
Associated Roadway Design:
Vollmer Associates
Geotechnical Engineer:
Haley & Aldrich
Lighting Design: Mintz
Lighting Group
|