|
Best of 2005 Awards
U.S. Post Office and Courthouse - Cadman
Plaza
Award of Merit: Adaptive Reuse
For more than 40 years, much of the castle-like U.S. Post
Office and Courthouse in downtown Brooklyn - with its corner
tower, turrets, dormers, and arches - stood mostly empty and
neglected. Now a $175 million adaptive-reuse project, completed
in August, has restored the landmark to its former glory.
The original four-story Romanesque revival-style building,
completed in 1892, long housed facilities for the federal
courts and post office. An eight-story addition completed
in 1933 significantly expanded the structure. But the building
was never fully occupied, and some parts have been vacant
since 1960.
The project team had the task of further expanding the existing
575,000-sq.-ft. structure to provide new facilities for the
U.S. Bankruptcy Court, U.S. Attorney, and U.S. Postal Service,
each of which had different access and security needs. And
the team had to restore the original structure, which looks
over Cadman Plaza.
"The design and construction issues were complex, requiring
a great deal of expertise in historic and adaptive reuse,"
said one juror.
The team added more than 85,000 sq. ft. of new space into
the 1933 addition, including a 41,840-sq.-ft. mezzanine between
the first and second floors and 9,300 sq. ft. carved into
each of the four upper floors. It built the space into a portion
of an interior courtyard.
In order to accommodate the expansion, the project team tested
existing materials, such as the cast-iron frame, to determine
whether it could be welded to a new steel frame. The tests
failed, requiring the team to instead bolt new girders and
beams into place.
The team also had to keep the 24-hour, seven-day-per-week
postal operation functioning during the project, which required
extensive protective measures to ensure customer and employee
safety.
The team had to address years of neglect and an aging infrastructure
in restoring the building's historic features. A survey found
that most of the elements could be restored, with the notable
exception of the plasterwork. The team's subsequent replacement
of the original plaster and moldings was one of the largest
projects of its kind in the city.
Specialty contractors restored and refurbished many remaining
historic details, including marble, mantles, and original
woodwork, and they also replicated missing or damaged elements.
In addition, the team recreated the 1892 color scheme by researching
original building documents and engaging in painstaking restoration
"detective work" - using solvents to strip away
years of paint from surfaces to reveal the original colors
and designs.
"The interior finishes were opulent and beautifully
designed and installed," one juror said.
The team also installed a new 4,500-sq.-ft. skylight in the
atrium, replacing a smaller skylight previously covered to
conform to blackout laws during World War II. During construction,
crews covered the opening with a prefabricated structure to
protect the atrium.
The project also involved removing and replacing all mechanical,
electrical, and plumbing systems, as well as replacing or
reinforcing masonry shafts to accommodate the installation
of new freight and passenger elevators.
The team built a monumental stairway along the western side
of the building that leads to three separate entrances constructed
to accommodate the differing access and security needs. The
team also installed blast curtains on all windows and placed
security bollards around the building's perimeter.
The project survived the bankruptcy of J.A. Jones Construction,
the original contractor. Bovis Lend Lease of New York restarted
and completed the project.
Key Players
Owner: U.S. General
Services Administration
Construction Manager-General
Contractor: Bovis Lend Lease
Program Manager: URS
Corp.
Architect: R. M. Kliment
& Francis Halsband Architects
M-E-P, FP Engineer:
Flack + Kurtz
Structural Engineer: Severud
Associates
Lighting Design: H.
M. Brandston & Partners
Landscape Design: Johansson
& Walcavage
Electrical Contractor:
Five Star Electric
Plumbing Contractor:
Botto Mechanical
HVAC Contractor: Heritage
Air System
Fire Protection: Active
Fire Sprinkler
Stone Restoration:
Aztec Service Group
Marble Restoration:
Artisan Tile and Marble
|