|
Best of 2005 Awards
Arch Street Rail Yard and Shop
Award of Merit: Mass Transit
The Arch Street Rail Yard & Shop Maintenance Facility,
completed this year in Queens for the Metropolitan Transportation
Authority, will service, maintain, commission, and store new
M7 trains for the Long Island Rail Road.
But the $79 million project is also an integral part of a
bigger construction program that will allow LIRR commuter
trains to travel to Grand Central Terminal, relieving tight
conditions at its only other terminus in Manhattan at Pennsylvania
Station. That program, dubbed East Side Access project, underscored
the complexity of linking the facility into the larger rail
grid.
"It was an unbelievably complicated job," said
one of our Best of 2005 judges.
Slattery Skanska of Whitestone, N.Y., with joint-venture
partner Edwards and Kelcey of Morristown, N.J., started in
July 2002 in what was the MTA's first use of the design-build
construction strategy. They completed the yard in March.
The project entailed building:
- the maintenance shop
- a 26 kV-class traction power substation and building
- an engineering support building
- a 1,000-ft.-long train cleaning platform
- a storage building and utilities
- and nearly 4 mi. of trackwork.
All work took place around an active freight yard operated
by the New York & Atlantic Railway. The 12-acre site had
previously served as a rail freight yard and material transfer
facility.
The team excavated and disposed of approximately 60,000 cu.
yd. of contaminated soil and drove 20,000 lin. ft. of H-piles
into rock to lay the foundation for the facility, which uses
15,000 cu. yd. of concrete. It also constructed an underground
utility network with 20,000 lin. ft. of water mains, sewer
and gas lines, and duct banks.
The 60,000-sq.-ft., steel-frame train maintenance building
has masonry and steel-panel walls and accommodates five tracks.
The team procured, installed and commissioned the train-shop
equipment, including platform elevator lifts, a gantry system
to allow access to the rooftops of trains, and hydraulic-action
folding doors measuring 16 ft. wide by 20 ft. high.
"It's a warehouse building with a lot of systems in
it," one of the judges said.
Within the contract's required 810 days, the team built the
facility largely from the outside in. It did not know the
machinery specifications or power requirements when it was
sizing the underground conduit, forcing it to install conduit
and floor slabs after it had constructed the shell.
Key Players
Owner: Metropolitan
Transportation Authority
General Contractor:
Slattery Skanska
Designer: Edwards and
Kelcey
Environmental Consultant:
TRC Environmental
Architectural Consultant:
Sowinski Sullivan Architects
Electrical: Egg Electric
Pile Driving: Underpinning
and Foundations Skanska
Rebar Material: Harris
Rebar Atlantic
Track Turnouts: Atlantic
Track & Turnout
Building Plumber: WDF/Greene
Masonry: Job Opportunities
for Women
HVAC-ATC-Sprinkler:
Peco Inc.
Drywall: Duncan Interiors
|