|
Best of 2005 Awards
Essex County Courthouse
Project of the Year: Rehabilitation and
Restoration
When
the Essex County Courthouse opened in 1906, Newark was one
of the state's most vital urban centers, with strong local
industries, a solid economic base, and the nation's first
county park system.
The courthouse's position along the slope that rises westward
from Broad and Market streets - a prominent city intersection
- gave it authoritative stature while providing scenic views
of and from the building. Designed by Cass Gilbert, whose
other works include the U.S. Supreme Court in Washington,
D.C., and Manhattan's Woolworth Building, the marble-clad
courthouse also has artwork from leading American Renaissance
artists.
But the structure had fallen into great disrepair over the
decades and finally closed, sitting vacant for 13 years while
court functions shifted to the adjacent Hall of Records building.
The project team faced great hurdles to restore the 180,000-sq.-ft.
facility, which is listed on the National Register of Historic
Places.
The $60 million project, which began in 1996, proceeded slowly
for years, with the exterior work finishing first in 1999,
followed by the completion of selective demolition and hazardous
materials abatement in 2001. The interior restoration began
in 2002, and the county finally put the project on an aggressive
timetable a year later. The facility reopened in March.
The work encompassed everything from the restoration of historic
features to installation of technological systems, such as
air conditioning, fire suppression, telecommunications, and
security. There also were upgrades to accommodate modern amenities
and the federal Americans with Disabilities Act.
Overseen by Tishman Construction's Newark office in a joint
venture with Century 21 Construction of Clifton, N.J., the
project had three phases, starting with the development of
a space allocation program for the Civil Division of the Superior
Court and a careful architectural and historical analysis.
The second phase involved cleaning and restoring the marble
façade, as well as replicating deteriorated decorative
elements. The team also restored large windows and nine marble
statues.
The most extensive phase was the third, which involved the
interior restoration and renovation. The work entailed adding
historical finishes and refinishing wood throughout the structure.
The team also restored 10 historic courtrooms and added a
new courtroom.
The third phase also involved replacing all building systems,
which in many cases required the team to find space for new
ductwork, conduits, piping, and air-handling equipment within
the existing structural configuration. The team chose to redeploy
an elevator for prisoners as the space for major ductwork
and conduit. It also adapted the original coal-storage chambers
to accommodate electrical service equipment and the original
boiler rooms to house heating and air-conditioning equipment.
The building is now fully wired for telephone and data communications,
including courtroom amplification systems for the hearing
impaired. The team also made repairs to the marble and granite
entrance stair and plaza, as well as to the building's drainage
system and roof.
A major restoration task involved the rotunda, which dominates
the eastern portion of the building. The rotunda - supported
on massive stone piers and ringed by staircases and open corridors
- is topped by a stained-glass Tiffany skylight and two smaller
side domes. The team reconstructed the skylight, cleaned the
stone, added fiber optic lighting, and restored paint surfaces
- in some cases removing colors from a 1929 restoration in
order to recreate the original 1906 finish.
The team even took on the restoration of the original furniture,
as well as 1920s-era pieces, including more than 400 chairs,
175 courtroom benches, 35 tables, coat racks, and umbrella
stands. The restoration of historic murals, fabric, and other
artwork involved analysis and craftsmanship by specialists.
One judge summed up the panel's admiration for the building
by saying, "I want to get arrested there, so I can visit
the courthouse."
Key Players
Owner: County of Essex
Architect: Farewell
Mills Gatsch Architects
Construction Management:
Tishman Construction; Century 21 Construction
General Contractor:
Cobra Construction
Materials Conservation:
Building Conservation Associates
M-E-P Engineer: Joseph
R. Loring & Associates
Structural-Civil Engineer:
Schoor DePalma
Mural Restoration:
EverGreene Painting Studios
Restoration Contractor:
Hall Construction
|