|
Best of 2005 Awards
New York Power Authority 500-MW Combined-Cycle
Power Plant
Award of Merit: Industrial
"Constructing a combined-cycle plant in New York City
is not an easy chore," one of our Best of 2005 judges
said.
That viewpoint captured the panel's admiration for the completion
of a new power plant on a four-acre site in the Astoria section
of Queens, adding 500 MW to New York's often-stretched power
supply.
The $327 million plant, slated for completion last month
on behalf of the New York Power Authority, is expected to
help the city meet its anticipated power needs for the next
few years. The plant, built next to the authority's existing
Charles M. Poletti Generating Station, will burn natural gas
with low-sulfur oil as a backup and use a combined-cycle technology
that is cleaner and more efficient than most plants.
Combined-cycle technology allows the plant to generate 50
percent more electricity from its fuel than it would with
a conventional single-cycle power system. The dual-phase system
essentially captures heat generated from the main natural
gas turbines and recycles it into additional energy.
The system has two gas-powered combustion turbine-generators
operating in conjunction with two heat-recovery steam generators
and a steam turbine-generator. The facility also has advanced
selective catalytic reduction emission controls.
"They craned in the big heat-recovery steam generators,
and just seeing what they went through to move those into
place is impressive," one judge said. "It's an extraordinarily
complex project."
The construction effort included erecting a 97,000-sq.-ft.,
two-story building to house plant equipment. The project team
installed, tested, and commissioned all of the equipment,
including two 160-ft.-tall steel stacks for the heat recovery
generators.
The project team drove 6,000 H-beam piles into the ground
to support the foundations for all of the facilities and equipment.
Other work included the installation of 110,000 ft. of process
piping, along with 500 monitoring instruments, a water tank
that holds 1 million gallons, and a 32-cell, air-cooled condenser.
The new plant's electrical systems include digital control
equipment, three step-up transformers, switch gear, 1.4 million
ft. of cable, 215,000 ft. of conduit, and 26,000 ft. of cable
tray.
"There is a lot of fine calibration and many structural
components," said one judge.
As many as 650 workers, representing 15 local labor unions,
worked onsite during the project, which had an aggressive
schedule for completion. Workers performed certain field activities
in shifts around the clock. The contractor team advanced construction
and mitigated changes even as the engineering team was finalizing
and issuing designs. <<
Key Players
Owner: New York Power
Authority
General Contractor: Slattery
Skanska; Gottlieb Skanska
Construction Manager:
DMJM Harris
Structural-Mechanical-Electrical-Geotechnical
Engineer: Sargent & Lundy
Steel: Helmark Steel
Concrete-Plumbing: Slattery
Skanska
Electrical: E-J Electric
Installation
Fire Protection: SIRINIA
Fire Protection
Insulation: Horizon
Contracting
|