|
Project
of the Year - Airport
AirTrain JFK Terminal at Jamaica
Station
Many consider the Long Island Rail Road's Jamaica Station
in Queens to be at the heart of the system. If so, then constructing
a terminal for the AirTrain JFK light rail system there was
like doing open-heart surgery.
One judge who agreed that Jamaica was a critical central
hub for LIRR said completing a new station there was tremendous.
"At Jamaica, because you have the active railroad running
and the freight railroad, you had extraordinarily complex
issues to deal with," the judge said.
The $389 million project created a multimodal transfer point
that links the new light rail system to the LIRR, New York
City Transit subway lines, and ground transportation systems.
The terminal in the Jamaica section of Queens - at the northwest
corner of 94th Avenue and Sutphin Boulevard - is about 3 mi.
from John F. Kennedy International Airport.
A major component of the project is the new Vertical Circulation
Building-Jamaica Central Control Building, a 250,000-sq.-ft.
structure with seven floors. The building enables passenger
connections to the AirTrain JFK system, and will feature passenger
baggage check-in facilities and flight-related information
in the future. That structure's architectural finishes include
glass and aluminum curtain wall, terrazzo floors, stainless
steel, marble, granite and veneer plaster walls, and metal-panel
ceilings.
The project also entailed building a new "portal"
structure over the LIRR tracks, with elevators, escalators,
and moving walkways that connect the new circulation building
to existing LIRR and New York City Transit facilities.
Finishing those connections also required work on the existing
LIRR facilities. That big job involved replacing all platforms
and canopies, platform facilities, and systems. On that portion,
the project team faced historic preservation requirements,
including approval from the New York State Historic Preservation
Office on platform canopy design to preserve the historical
nature of Jamaica Station.
The LIRR station also entailed renovating the stairs from
platforms to street, replacing the existing Westerly Bridge,
and reconfiguring Sutphin Boulevard between Archer and 94th
Avenues, adding a new street concourse. A final phase is demolishing
the LIRR's existing transfer mezzanine and stairways from
street level at Sutphin Boulevard, replacing them with new
stairways to the LIRR platform level.
The project also involved expansion and renovation of the
existing subway station mezzanine. Three new high-capacity
elevators in the subway mezzanine space shuttle passengers
between subway, street, and portal levels.
Completing construction within the busy stations of LIRR
and the Sutphin Boulevard/Archer Avenue subway stations required
installing varying temporary and permanent design features.
It also required integration with railroad and transit operations
-including 54-hour weekend track outages - as well as detailed
construction planning and staging to minimize disruption to
riders.
Other efforts to minimize disruption included maintenance
and protection of traffic, community outreach, vibration monitoring,
and condition surveys. The project crews performed work during
off-peak hours whenever possible and limited their use of
cranes on the street. The project team had materials delivered
to the site - and debris removed - by rail.
The project, jointly sponsored by the Port Authority of
New York and New Jersey and the Metropolitan Transportation
Authority, got its financing from capital funding from those
agencies and from passenger facility charges.
But the project required coordination of other agencies
and organizations beyond the Port Authority and MTA, including
LIRR, New York City Transit, the city's Department of Transportation
and Department of Environmental Protection, Con Edison, Keyspan,
and local community groups.
The design of the terminal also envisions future expansion.
It allows for an additional 10 stories as well as baggage-handling
and security-screening systems.
|