|
Project
of the Year - Adaptive Reuse
Towers at 455 Central Park West
The building at 455 Central Park West - once an eyesore
at 105th Street in Manhattan - has become an attractive addition
to an upscale neighborhood.
The $106.9 million project involved construction of a new
26-story high-rise luxury condominium building with 81 units
and the restoration of a four-story, chateau-style landmarked
structure with 17 units. The renovated landmarked portion
of the property offers family-sized residences that feature
circular living rooms, bedroom suites, vaulted ceilings, and
oversized gothic windows.
"The project team took a derelict, old building that
had been vacant for 20 years and gave it a massive rehabilitation
and new use," said one judge.
John Jacob Astor III originally built the landmark in 1884
as the New York Cancer Hospital. In the 1950s, it became the
Towers Nursing Home, which later closed. Since the mid-1980s,
the property changed ownership several times, attracting several
development proposals. None took hold until construction on
the new condominium project began in December 2002.
Restoring the older structure was a big job for the construction
team, since the landmark face is the only remaining feature
after the team gutted the interiors. A restoration subcontractor
repaired the historic façade by repointing, replicating,
and restoring where necessary - a task that involved casting
new brownstone elements to repair damage sustained over the
years. That took place while other superstructure work was
ongoing, requiring the team to temporarily brace the façade
with steel beams while pouring the new concrete floors and
columns in place.
After pouring the concrete floors, the project team began
building a new roof, replicating features of the historic
structure. The work included capping off the turret towers
with new cone structures and constructing mansard roofs. The
primary materials for these jobs were structural steel, light-gauge
metal, and plywood sheathing. The finished product showcases
natural Vermont slate, lead-coated copper gutters, dormers,
and custom finials.
The roof construction was a distinct challenge. The project
team designed and installed the new light-gauge truss gable
roof system while maintaining and restoring the existing wood
cathedral ceiling below it. Design and installation of the
new light-gauge cones above the landmarked turrets required
a tremendous amount of coordination between the carpenter,
slate roof installer, skylight installer, and several other
trades. Similarly, design and modification to existing cast-iron
cones on two of the four turrets required careful coordination
to create new openings for 11-ft.-long and 8-ft.-wide skylights.
Another challenge was designing and installing a new boiler
flue system within the existing brick chimney in another turret.
That task required the subcontractor to install a 90-ft. section
of flue into the existing chimney, along with modifications
at the chimney's top to include draft inducer fans that had
to be hidden from view.
At the same time the project team was renovating the landmarked
structure, it was building a new mid-rise luxury tower in
close proximity. This required extensive planning and coordination.
For example, the team poured the superstructure for both
the tower and landmarked portion at the same time. In addition,
the team had to extend connections to major mechanical elements
such as boilers and domestic hot water heaters, which are
in the landmarked building's cellar but serve both buildings.
The two-structure assignment translated into a lot of sitework
as well. The highlights included construction of a central
courtyard between the buildings, a complete site drainage
system, a cobblestone circular driveway, and bluestone paving.
The project team also paid special attention to details
of public spaces within the new building. Many of those lobbies
and corridors feature curved GFRC ceiling systems and vault
groin ceilings - including design elements intended to match
the existing landmarked building.
Accordingly, the lobbies and apartment corridors feature
custom wood arched portal passageways with dark anodized bronze
bass. The package room in the main lobby is fully wrapped
in frosted glass and decorative bronze panels. Capping the
detail throughout the building is how elements like the terrazzo
flooring pavers, window grilles, exterior railings, package
room, and elevators all repeat the original rosette design
found in the landmarked structure's railing.
|