|
The Judy and Arthur Zankel Hall
What more can you say about a project that required removing
nearly 7,000 cu. yds. of rock from underneath a 110-year-old
landmark structure, all without interrupting the daily operations
of Carnegie Hall?
"What an unbelievable project!" said one jury panel
member.
And another member said the panel's decision to grant the
Judy and Arthur Zankel Hall an award was "a no brainer."
The project created a $72 million, 644-seat, 41,000-sq.-ft.
flexible performance and education space on a 20,000-sq.-ft.
footprint beneath Isaac Stern Auditorium. Carnegie Hall vice
chairman Arthur Zankel and his wife, Judy, gave a leadership
gift to the project.
From a technological standpoint, Zankel Hall is a 21st Century
venue. It has three primary seating configurations - accomplished
with the use of nine floor lifts and 12 chair wagons and 212
adjustable ceiling trusses for lighting and other theatrical
equipment.
When Carnegie Hall opened in 1891, it had three auditoriums:
the Main Hall (now Isaac Stern Auditorium) at the ground level,
the intimate Chamber Music Hall (now Joan and Sanford I. Weill
Recital Hall) several floors above West 57th Street and the
lower-level recital hall (now Zankel Hall.)
The three auditoriums have gone through many physical changes
over the years, but none more than the lower level.
Prior to its transformation into Zankel Hall, the space was
rented by Cineplex Odeon to be used as a movie theater. When
the cinema's lease expired in 1997, Carnegie Hall decided
to reclaim the space for music, but decades of makeshift renovations
had rendered the space irreversibly compromised.
Carnegie Hall's basic design criteria were to create an intermediate-sized
performance venue with excellent acoustics, which was contemporary
in style yet sensitive to the landmark building above. The
space would double as an educational facility and accommodate
the latest in contemporary communications technologies.
Functionally, the main floor of the auditorium consists of
a series of lifts, constructed atop screw jacks, which move
up and down. The theatrical seats on the main floor area affixed
to chair wagons, constructed atop air casters, which move
in and out of an adjacent storage "garage." The
lifts and chair wagons in tandem enable the auditorium to
be reconfigured, including three different-sized end stages
- an end stage with orchestra pit, center stage and flat floor.
The ceiling of the auditorium consists of remotely controlled
steel trusses that move up and down, allowing theatrical equipment
to be readily repositioned to accommodate the different stage
positions and to fulfill production requirements for a diversity
of events.
Imbedded at the infrastructure level of the auditorium floor
and ceiling are conduit and wiring to allow lighting, sound,
video, communications and recording equipment to be placed
virtually anywhere as needed.
Work on Zankel Hall began in spring 1999 with the removal
of bedrock. Before excavation could proceed, the team relocated
existing mechanical utilities from the structure, including
miles of piping and wiring.
Construction materials for the job had to be transported
to and from the site through a 10- by 20-ft. opening in the
sidewalk. Workers installed a 20-ton hydraulic custom elevator
to transport all construction equipment through the sidewalk
opening, and bulldozers were taken apart to fit through the
opening, and then reassembled below ground. All rock was removed
in 4-cu.-yd. boxes using forklifts.
Workers installed a complex temporary shoring system made
of steel supports. To support Isaac Stern Hall's seating area,
workers drilled caissons 30 ft. below the excavation line
and installed 12 temporary columns to support the structure
above. Then loads were transferred to new structural elements.
The team performed an extensive structural demolition to remove
walls and concrete slabs from the existing space.
With the N and R subway line as close as 9 ft. to Zankel
Hall, the team established a rock-monitoring program that
consisted of numerous seismic monitors to detect vibration.
The ceiling of Zankel Hall below Stern Auditorium is suspended
on 6- by 9-ft. steel beams and supported on rubber pads to
isolate sound and vibration.
|