|
Time Warner Center
If the sheer size of the Time Warner Center - 2.8 million
sq. ft. - doesn't impress you, then consider the numbers.
Multiple general contractors, 90 subcontractors, half a dozen
architects and more than 2,000 workers pitched in to create
the $1.7 billion project at Columbus Circle. They used 27,000
tons of steel, 101,500 cu. yds. of concrete and one million
sq. ft. of curtain wall.
"This was a mind-boggling effort," a jury panel
member said. "The size, the complexity, the coordination
required was incredible."
The project includes the new world headquarters for Time
Warner, the 1,970-seat Jazz at Lincoln Center, The Shops at
Columbus Circle, 199 condominiums, the 251-room Mandarin Oriental
Hotel, 200,000 sq. ft. of office space and a 504-stall valet
parking garage.
Despite the project's size, it was completed in 36 months,
on time and within budget - no small feat for a project that
was decades in the making. From the start, the team knew that
the success of the project would hinge on its ability to find
effective solutions to overcome the challenges that invariably
would arise with a project of this magnitude.
The team's first order of business was to devise an organizational
structure that would be capable of handling project oversight.
Under the guidance of the project director, four project
executives were assigned to oversee - through their project
managers and project superintendents - distinct areas of the
building, including the podium, towers (with both residential
and hotel functions), the site work and the mechanical, electrical
and plumbing systems.
To manage costs of the project, full-time accounting, estimating
and change management personnel were put into place and met
weekly with the development team.
The project plan room, where five plan coordinators distributed
design and shop drawings to more than 75 consultants and 100
contractors, likely exceeded the size of most onsite project
offices. The intricacies of maintaining a full project schedule
at times required two full-time schedulers to update the progress
of over 5,000 procurement, design and trade activities. At
its peak, the construction manager's staff numbered 110 personnel.
Once the foundation was completed, steel erecting began in
a hole that occupied two city blocks. The site was so large
that, at one time, five cranes were needed to reach every
corner. For the majority of construction, four cranes were
used, one in each quadrant of the building. Two cranes were
able to pick from 58th Street and two from 60th Street.
One challenge was encountered when more than one crane was
needed to pick up equipment or other materials.
For example, two cranes were required to place the generators
and chiller machines on the 22nd floor within the structure's
complicated truss framework. For these picks, the crane of
the southeast corner of the site picked the units from the
east end of the building and handed off the units to the southwest
crane over the middle of the 24th floor, which then dropped
the units through the openings on the 23rd and 24th floors
onto the 22nd floor.
Design changes also presented some problems. While the project
team had anticipated changes, it did not expect the number
of changes to the structural steel package. At the height
of construction, a combined three tons of steel were shipped
to the site weekly and more than 10,000 detailers and draftsmen
were employed by firms from Canada to New Zealand to handle
the level of detail required for steel erection.
After the steel was in place, the project also faced challenges
with the installation of the massive transfer trusses at the
base of each tower. The concrete encased trusses support the
cast-in-place concrete towers and house the MEP systems for
the entire building and required thousands of hours of planning
prior to installation.
To study the logistics prior to construction, two balsa wood
models of the steel trusses that included removable walls
and floors were developed. Each truss floor houses chillers,
generators, air handlers, 24-inch pipe and switchgear and
required substantial coordination between the concrete contractor,
steel fabricator, construction manager, architect and engineer
during installation.
To vertically transport workers and materials at a speed
and capacity necessary to meet construction schedule demands,
two hoist towers were erected, one on 58th Street and one
on 60th Street. Each tower had four high-speed rack-and-pinion
cars and one material hoist. During the peak loading times
of morning and lunch, it was necessary to run two of the cars
on an express basis to upper floors.
A factor complicating the hoist tower arrangement was the
setback distances, especially for the south tower complex.
To accommodate the setbacks and speed at which the hoist towers
were to be erected, a customized system of tower sections
and prefabricated truss ramps were placed into service by
tower cranes. Two additional masonry hoists were constructed
on the building interior to transport masonry and mortar materials
to the first 12 floors.
Transporting workers and materials on the inside of the building
also required coordination. More than 600 workers were needed
to work daily on the north tower alone, which required staggering
work schedules to minimize wait times for the elevators.
Because of the project's history, the community took much
interest in the development of the site, which required the
project team to be in communication with four local community
boards. Severe restrictions were placed on the construction
team with respect to deliveries and working hours.
At one point, it appeared as if communication between the
project team and community boards was going to break down,
but the two sides tried to work through difficulties with
safety, noise, dust control and deliveries.
|