|
Times Square Tower
Construction of the Times Square Tower was the last office
component of the 42nd Street Development Project, and the
site and logistics made it a tough job to complete.
The Times Square subway station surrounds the site on all
four sides. The No. 7 train runs along the south side of the
building, the No. 1/9, 2 and 3 trains run along the west and
the N, R, Q and W trains run along the east. During peak times,
10,000 pedestrians cross Seventh Avenue each hour.
"This is a world-class structure," said a jury
member. "It was a tough site, with amazing logistical
challenges."
The 49-story tower with 1.2 million sq. ft. encompasses a
full-block site at 42nd Street and Seventh Avenue. Since 1995,
the 42nd Street Development Project, a subsidiary of Empire
State Development, has overseen 6.4 million sq. ft. of new
redevelopment, 6,000 new theater seats in restored historic
theaters, 8,600 new movie seats, 600,000 sq. ft. of new retail
and restaurant establishments more than 1,300 new hotel rooms.
Among features of the Times Square Tower are a ground-floor
lobby with a shuttle elevator connection to a main sky lobby,
a curtain wall consisting of 11 different materials and commercial
signage symbolic of the Times Square revitalization theme.
The $229.7 million project also included building a new subway
entrance within the footprint of the building. As part of
this project, two floors of the station had to be renovated
and passengers had to be reverted away from construction without
disturbing access to trains. The New York City Transit Authority
required the station to open prior to completion of the base
building and storefront.
Because of the logistical challenges of the site, the project
team had to be in constant communication with the New York
Police Department, the New York City Department of Buildings
and the Transit Authority. Surrounding streets had to be closed
during the picking of steel and mechanical equipment as well
as erection and dismantling of cranes.
Activities were scheduled for Saturdays, Sundays and after
hours to avoid interfering with the crush of pedestrians during
rush hour.
Building the new subway station also required coordination
and communication with the Transit Authority and 42nd Street
Development Project. Full-height temporary partition walls
were erected within the station to separate the passengers
from the construction activities, temporary signage was erected
to notify and redirect passengers and a temporary storefront
was erected to open the station prior to the beginning of
storefront work.
The project team also had to face obstacles in construction
of the curtain wall. Continuous site visits were made to the
curtain wall manufacturers' fabrication and assembly plants
in Canada and Connecticut, and curtain wall performance mockup
tests were performed and monitored in Florida.
Oversized curtain wall panels were hoisted using cranes,
and the curtain wall was installed using "beech hoisting
equipment," a mobile arm that reaches over the building
and supports the cables that hoist the panel from the floor
below and lift it into place.
Times Square Tower was another project that broke ground
prior to Sept. 11 but faced additional security concerns in
the wake of the World Trade Center attacks.
To address those concerns, all perimeter column, beam and
diagonal steel sections from the ground to the second floor
were reinforced after erection was completed. A separate contractor
was hired so as not to interfere with erection pace.
Lobbies were redesigned to include turnstiles, better surveillance
and enhanced security measures.
|