|
Route 9A Emergency Reconstruction
The ripples of the Sept. 11, 2001, terrorist attacks spread
far beyond the World Trade Center site.
One sector sustaining heavy damage was transportation-including
the Route 9A corridor in Lower Manhattan that links Battery
Park City and the World Financial Center to the rest of the
city.
Reopening that segment of West Street turned out to be a
major effort because of the massive scale of cleanup and an
emergency schedule for road reconstruction. But the $5 million
job was a success-with the road reopening in just six months.
The New York State Department of Transportation assembled
a team of agencies and contractors to take on coordination,
planning, difficult logistics and a rapid timetable.
Primary challenges in the three-month cleanup phase involved
creating alternate work areas for WTC site-recovery traffic,
reconnecting and relocating utilities and securing project
funding.
The jury cited those multiple tasks, with one member saying:
"This was a usual highway job made unusual by the complexity
of the utility work. If operation was lost at any time, there
were significant consequences. This was logistically difficult
and a very impressive job."
A major early focus was creating work areas and facilitating
debris removal. With Pier 25 designated for barge loading
of debris, the project's civil engineers created a temporary
haul road by replacing and paving over part of an existing
bikeway.
This allowed trucks to proceed directly to the barge transfer
site without using the 9A roadway. The project team also paved
over a parcel west of Route 9A and north of Pier 25 to create
a staging area for WTC rescue, recovery, security and support
services.
As WTC cleanup operations continued, the project team took
on the second three-month phase-designing and constructing
a six-lane interim roadway for Route 9A traffic that included
temporary bridges, sidewalks and crosswalks.
First, the team needed to complete an order-of-magnitude
cost estimate in order to qualify for Federal Emergency Management
Administration funds. That meant it had to inventory Route
9A from the Battery Tunnel to 59th Street to determine the
needs for reopening and restoring the road to its prior condition.
After securing the federal funds, the team chose an alignment
for the six-lane interim roadway that balanced traffic needs
with the recovery operation's cranes, temporary utilities
and work areas for the crews. The potential alignment also
had to plan around the WTC site's "bathtub" retainer
wall.
The engineers mapped an alignment that met all of those needs,
while also avoiding encroachment on Battery Park City's commercial
center, bridging over PATH train structures, preserving the
temporary haul road and ultimately restoring Route 9A between
Chambers Street and the Battery Tunnel.
Another key project success was quickly replacing damaged
infrastructure-including water mains, telephone lines, drainage
and electric conduits-by integrating those new utilities into
the overall construction plan for the interim roadway.
Construction proceeded on a 24-hour, seven-day-a-week schedule.
It required vast coordination among agencies and teams installing
sidewalks, crosswalks, temporary bridges, traffic lights and
roadway lighting.
That coordination included the New York City departments
of transportation and design and construction, the Port Authority
of New York and New Jersey, Battery Park City Authority and
various other city and state agencies.
|