|
Port Elizabeth - Wharf Improvements - phase one
Upgrading the Port Elizabeth Marine Terminal in New Jersey
to handle ship and container traffic of the future called
for increased water depths, larger crane loads, increased
berthing and mooring loads, and seismic loading capability.
That translated into a big job-massive dredging, power supply
upgrades, installation of new piles and cranes, and fully
replacing the fender system. And that was the first of five
phases to overhaul the 30-year-old wharf operated by APM Terminals
North America Inc., which leases it from the Port Authority
of New York and New Jersey.
The major goal was to equip the wharf with cranes handling
the latest generation of Super Post-Panamax containers, to
provide approximately 1,000 ft. of berth for the corresponding
container vessels and to allow for a future dredge depth of
-50+2 ft.
Phase one of the project, which cost $15.8 million, was completed
in a year.
The design's heart was installing a king pile cutoff wall
along the wharf surface to permit deeper dredging for upgrades
to accommodate future increases in container vessel and crane
capacities.
After evaluating and assessing the wharf's stability under
both static and seismic loading conditions, the project team
chose an anchored king pile system along the face of the wharf
as the most cost effective solution. This involved installing
new pipe piles to support the waterside crane rail and a combination
of existing and new H piles to support the landside crane
rail.
The choice also allowed for a shorter construction timetable
than complete demolition and replacement of the wharf. The
design's H-Z wall system took advantage of limited rock obstruction
in the embedment-avoiding an expensive pipe-Z wall system.
The jury appreciated the design's complexity, saying, "This
project was like trying to resole shoes while someone was
still wearing them. It's extremely complex. For example, they
put a pile system inside an existing pile system."
The pile design also preserved a fish habitat-and access
for inspection and maintenance under the wharf-by cutting
intermediate (Z-shaped) sheet piles before the deck, above
the existing mudline. Since the king piles transfer the entire
load to the deck, there is room beneath the existing wharf
for fish to migrate.
Another major facet was installing a new fender system to
absorb the energy from 152,000-metric ton container vessels
as well as barges. The new system uses discrete resilient
rubber fender units on the nonbarge portion and a steel panel
system linked by hinges, with timber facing, at the barge
berth.
It is more flexible than standard fender systems, which aren't
suited to harder-to-steer barges that are more likely to hit
fenders.
Upgrading and expanding the power substation-including replacing
and adding transformers-was also a critical phase-one element,
especially for meeting future crane installation needs. By
project's end, 16 cranes will be in place, requiring a doubling
of substation capacity and a new sitewide distribution system.
The project also involved upgrading tie rods to resist higher
mooring loads, cutting a new cable trench along the wharf
to supply electric power to the cranes and upgrades to the
paving and drainage systems.
|