|
Niagara Gorge Access Project
Talk about working conditions.
It's the dead of winter in upstate New York and 85-mile-an-hour
winds and an icy mist are blowing off the thundering waters
of Niagara Falls.
And you're on top of a 20-story-high structure, attaching
18- by 6-ft. mirrored glass wall sections onto a new 260-ton
galvanized steel frame. And, there are more than 750,000 gallons
of water falling each second only 100 ft. away.
"Wow!" one jury member said about the project
team responsible for building a new 200-ft.-tall observation
tower beside the sheer Niagara Gorge of the falls. "I
was impressed by the working conditions, the site logistics,
the tough location, the fact that it was done in the winter
and rebuilt from the top down."
The new observation tower provides access for millions of
people each year to view the falls, to travel down into the
gorge and to ride on the Maid of the Mist boat into the waterfall.
New high-speed elevators were installed to service nearly
700,000 visitors each summer. The project cost $20 million.
To minimize interruptions in the operations of the New York
State Parks and the Maid of the Mist tours, the construction
schedule was restricted to the eight off-season months from
October to May. Much of the work progressed seven days a week,
24 hours a day.
With the project site in the Niagara Gorge and adjacent to
the Niagara River, the area was impacted by a "microclimate"
that could change in a moment. During the cold winter months,
the wind would carry the mist created by the falls across
the project site and leave behind a treacherous coating of
ice.
To handle the problem, the project team provided a 200-ft.-tall,
freestanding, shrink-wrapped scaffold enclosure surrounding
the existing tower.
The enclosure was anchored by 24 rock anchors, embedded 35
ft. into the bedrock of the lower Niagara Gorge. It provided
a safe haven for work on the towers throughout the winter
months and also provided a pair of scaffold stairs for personnel
access to and from the lower gorge.
The scaffold enclosure - which was only designed to withstand
65-mph winds - worked effectively except for two, one-week
periods when winds were clocked in excess of 85 mph.
A temporary metal deck platform system was suspended below
the existing bridge trusses. This system acted as a debris
catch, a working platform, containment for the lead-based
paint removal and recoating operations, and access from the
upper gorge to the scaffold.
To meet the schedule and quality control requirements of
the project, the project team required that the new structural
steel for the tower be prefinished. That raised two concerns:
The risks associated with erecting prefinished steel exposed
to the misting from the falls and cost and quality assurance
issues pertaining to touch-up requirements after erection.
In response to these concerns, the project team proposed
an alternate finish, hot dipped galvanizing. The result was
savings of $107,000, a slip-resistant finish that allowed
erection in even wet conditions and the virtual elimination
of any field touch-ups.
While the scaffold enclosure provided protection from the
wind, it was required to remain open at the top to hoist materials
in and out of the tower. It was, therefore, not heated.
Due to the conditions and the demand of the schedule, the
project team requested that the structural engineer design
the new structure with all bolted connections. The project
team worked closely with the steel erector to identify large
bents of structural steel that could be preassembled in the
upper gorge and lowered into place with the project crane.
These massive sections of steel were lowered through the
existing bridge trusses and then down into the scaffold enclosure,
using a crane stationed 230 ft. away. The countless hours
spent determining permissible bent sizes were regained many
times over when 259 tons of structural steel, all levels of
grating and the center stair tower were erected in 24 days
in the dead of winter.
|