|
Hudson Crossing
If Hudson Crossing had been built in another location, the
$75 million project would have been unremarkable. But at 37th
Street and Ninth Avenue, the building is surrounded by three
entrances to the Lincoln Tunnel.
Despite dealing with a 24-hour-a-day, seven-day-a-week traffic
flow, construction never tied up cars going into the tunnel.
"The team took a very messy site and delivered a nice-looking
residential building, three months ahead of schedule and $4
million below budget," remarked a jury panel member,
about the $43 million project. "It's impressive that
it never interfered with traffic."
Hudson Crossing, a 15-story, 259-unit residential apartment
complex, is a reinforced concrete structure with two levels
of below-grade parking for 160 cars. With a masonry exterior
and brick façade with punched-aluminum windows and
granite entry, it has 5,000 sq. ft. of retail space on the
ground floor for a total gross floor area of approximately
215,000 sq. ft.
The complex amenities include concierge services, 24-hour
security, exercise room, terrace, advanced telecommunication
services, laundry facilities, a roof deck and tenant storage
areas. The apartments have through-wall air-conditioning units,
imported stone countertops, wood flooring throughout the living
area and tile flooring in the kitchen and bathrooms.
Due to logistical constraints posed by the Lincoln Tunnel,
access to the site was restricted to a single location on
37th Street. This required the project team to be in constant
communication with the Port Authority of New York and New
Jersey and the New York City Police Department to coordinate
excavation, debris removal and deliveries of construction
material.
The terrorist attacks of Sept. 11, 2001, hampered the project
- which broke ground in January 2002. The Port Authority official
the team had been working with prior to construction died
in the terrorist attacks and original blueprints and plans
for the building stored at 1 World Trade Center were destroyed.
Access to the building was constrained by heightened security
measures adopted after Sept. 11. Construction workers and
vehicles were constantly stopped, searched and required to
show identification, which slowed the construction process.
The project team also had to deal with a 40-ft. retaining
wall along the 36th Street entrance to the Lincoln Tunnel.
With the use of a 24-hour electronic monitoring program that
determines movement in the wall, excavation and rock removal
was completed without compromising the wall's integrity.
The team established an auxiliary netting system around half
the building to prevent loose material from disturbing the
wall's stability or impacting traffic entering the tunnel.
To minimize interruption of traffic flow into the Lincoln
Tunnel during installation of utility services, the team determined
that the utility companies should work at night and implemented
an overtime program with Con Edison, which required a tremendous
amount of effort and cooperation with the unions and municipal
agencies.
|