|
Rehabilitation of Whitehall Street Fan Plant
Rehabilitating a fan plant for New York City Transit is an
intricate job, requiring rigorous testing, tight construction
specifications and difficult logistics.
It's all part of the work list for the project team rehabilitating
the fan plants at Whitehall Street and Furman Street in the
Montague Street Tunnel.
Asked to work on only one at a time, the project team focused
first on the Whitehall Street fan plant, turning it over to
NYCT's Operation Division in April. Completion entailed passing
a 100-hour endurance test, clearing it to provide life-safety
emergency ventilation service for the tunnel.
It was "a very difficult project that had a zero tolerance
for mistakes," a jury member said.
The $23.5 million project scope involved demolition of an
existing street-level building, construction of a new building
and installation of new electrical power and ventilating equipment.
It also entailed reconstruction of 250 lin. ft. of transition
tunnel, 85 ft. of vertical shaft and 15,000 lin. ft. of fireline
replacement.
Constructing the building's foundation involved installing
a sheet-pile bulkhead in the East River around three sides
of the new building's footprint. It also required the installation
of cast-in-place piles with steel casings.
Work on this piece of the project was conducted from barges
in the river, which offered mobility for the piling equipment.
While surveying to replace deteriorated sheet piling, the
project team found a 36-in. cooling water intake pipe and
a 48-in. outfall pipe that served the HVAC systems for several
downtown buildings. The pipes were below the mud line and
in an area where the team planned to install barge spuds.
To eliminate the risk of hitting those pipes during installation,
or of a barge resting on the cast iron pipes at low tide,
the team quickly redesigned project specifications, losing
no time on the schedule.
Congestion and tight spacing at the site provided broader
challenges for the
project team. The site had trailers on the north side, the
historic but deteriorating Battery Maritime Building on the
south and South Street traffic and pedestrian lanes to the
west.
That forced the team to work from the building footprint,
and to make a careful decision to use an existing 25-ft. diameter
shaft, with its 4-ft.-thick walls, as part of the support
for a 200-ton crawler crane - so it wouldn't block South Street
traffic.
The tight spacing also impacted the topside work of installing
the reinforced concrete building foundation, steel erection
and final architectural cladding. That work was done in an
area only large enough to accommodate a tractor-trailer.
Meanwhile, the team simultaneously handled steel erection,
electrical work, fireline work and ventilation equipment installation
in the tunnel.
Another delicate task came in removal of sheet piling on
the structure's north side, adjacent to the pipes and near
the vertical shaft. The team used a vibratory hammer to prevent
vibration from stressing the Maritime Building or the shaft
already in use as support for the crane.
|