|
300 Madison Ave.
Traffic can make a construction job more complicated than
it needs to be. The team of 300 Madison Ave. had to deal with
not just pedestrian and vehicular traffic, but rail traffic
as well.
The project team erected a 35-story, 1,080,000-sq.-ft. office
tower with ground-floor retail and two below-grade concourse
levels for office and support functions to serve as the U.S.
headquarters for Canadian Imperial Bank of Commerce World
Markets.
Two major subway lines, the shuttle between Times Square
and Grand Central and the No. 7 train, run just below the
north end of the site, next to two side elevations of the
lower floors of the building. The $800 million project, which
also includes the refurbishment of the subway station entrance
at 42nd & Madison, sits on Madison, between 41st and 42nd
streets.
Because of the challenge presented by the railways, the foundation
- conventional spread footings bearing on bedrock - was built
within just eight months using various techniques to separate
the earth from the existing walls of the subway tunnels. The
construction was phased in four sections within the one-acre
site to keep to the foundation schedule so that the structural
steel could be put in place on time.
The structural steel, concrete, fireproofing and aluminum
curtain wall were all completed within nine months.
The project broke ground in June 2001 and was fast-tracked
to be completed within 26 months. Drawings and designs for
the glass and granite structure were being issued as construction
began.
At the same time, logistics of each phase were altered to
meet the needs of the public and city traffic. Structural
requirements were even changing once construction started
- after Sept. 11, the construction team added approximately
$4 million to the construction costs in order to improve the
lower columns, fireproofing and structural connections.
The jury said the project achieved its goals for timely completion
of a terrific structure in a tough location. If the structure
and teamwork were not in place on the job, it would have been
difficult to complete.
Indeed, it was not "completed" all at one time.
The schedule was set so that blocks of floors were turned
over to CIBC and the other tenants as they were completed.
To do so, the project team used several designated temporary
roofs and stair enclosures in addition to a number of programs
to prevent the growth of mold and damage to the finished areas.
|