Penn Station
East End Concourse
Development Team
OWNER: New Jersey Transit, Newark, NJ
FACILITIES/RR OWNER: Amtrak, NYC
DESIGN ENGINEER: Jacobs Civil Inc., Edison, NJ
ELECTRICAL CONTRACTOR: Eldor Contracting Corp., Holbrook,
NY
PLUMBING CONTRACTOR: Taggart Associates, Long Island
City, NY
HVAC CONTRACTOR: FW Sims Inc., West Babylon, NY
MARBLE CONTRACTOR: Port Morris Tile & Marble
Corp., Bronx, NY
ORNAMENTAL IRON WORK CONTRACTOR: FMB Inc., Harrison,
NJ
DECK CONTRACTOR: Gottlieb Skanska Inc., Valley Stream,
NY
MINI-PILE CONTRACTOR: Urban Foundation/Engineering,
Elmhurst, NY
GENERAL CONTRACTOR: Yonkers Contracting Co. Inc.,
Yonkers, NY
CONSTRUCTION MANAGER: O'Brien Kreitzberg, NYC
The new $115 million East End Concourse for New Jersey Transit
(NJTransit) is making life easier for the thousands of commuters
who pass through New York's Penn Station each day. The concourse
links 8th Avenue to 7th Avenue below Penn Station and features
ticket windows, destination signage and retail space.
But the project itself was not easy. It involved the creation
of 55,000-sq.-ft. of space within two other structures. Some
team members called it "a station within a station."
The East End Concourse consisted of three different design
contracts: a temporary construction deck contract, an asbestos
abatement contract and the final East End Concourse contract.
The multiple contracts were issued as a means of facilitating
the construction.
The entire project actually consisted of the demolition and
reconstruction of 55,000 sq. ft. of space in the southeast
corner of Penn Station (Seventh Avenue and West 31st Street).
The reconstruction involved the creation of a new station
for NJTransit within Penn Station.
One of the team's most difficult tasks was working within
two existing structures. These included the current Penn Station
structure that was built in 1906 and the 2 Penn Plaza building
built above it in 1964. In addition, the team had to devise
a way to provide to provide vertical access off the platforms
within this maze of other structures. All of the work was
done up to 50 ft. below the street. As such, access to the
project and for getting materials in and out proved daunting.
To get materials in and out of the underground jobsite, a
hole was made though a street planter that fronts Penn Station
parallel to West 31st Street. To do this, an easement agreement
was entered into with Vornardo, the property owner. The hole
was 9-ft. wide by 16-ft. long, according to various development
team members.
This "entrance" allowed the movement of more than
900 pieces of steel totaling 300 tons - some pieces up to
30 ft. long - into the construction site. A 35-ft. high cherry
picker was used to lower each piece of steel into the hole.
Underground, rigging, chain hoists and trolley systems were
used to move the steel about.
In order to build above the existing platforms and live tracks
used by NJTransit and Amtrak, a temporary, 40,000-sq.-ft.
wooden deck was built and used to build the rest of the project.
In addition, new foundations were constructed at the track
level while minimizing disruption to commuters and train traffic.
This was done by erecting barricades on the platforms and
then staging the construction so the platforms could remain
operational
Demolition and construction not only required phasing the
work, but having to shut down two tracks at a time, usually
from 11 p.m. to 4 a.m., Monday through Friday.
The schedule, however, had to be constantly revised. Utilities
inhibited a smooth and continuous workflow. In fact, there
were so many utility lines that had to be identified, tagged
and relocated that one team member said "it was like
spaghetti down there."
The team also had to find ways to perform the necessary work
without having to have tracks taken out of service. The solution,
developed by the mini-pile subcontractor, consisted of customized
drill rigs to install the mini-pile foundations without having
to have a track taken out of service.
In addition, Amtrak personnel had to be moved around during
construction of a water meter room in the same location as
an electrical substation.
To move Amtrak personnel around, swing space was constructed
each time personnel had to be relocated. The water meter room
had to be constructed in a space that houses an electrical
substation. To accomplish and maintain the electrical substation,
a workaround was designed.
The jury said, "This project team faced a different level
of complexity (than the Times Square Station complex) by working
in an area that was not intended for its intended use. The
project also accommodated the shift of passenger traffic to
PATH North after Sept. 11, 2001, and the project team accomplished
everything one-year ahead of schedule."
|