Toys 'R' Us
in Times Square
Development Team
OWNER: Toys 'R' Us, Paramus, NJ
ARCHITECT: Gensler, NYC
INTERIOR DESIGNER: Joanne Newbold Associates, NYC
STRUCTURAL ENGINEER: Glisanz Murray and Stefick,
NYC
MECHANICAL, ELECTRICAL & PLUMBING ENGINEER: FMC
Associates, NYC
LIGHTING CONSULTANT: Focus Lighting, NYC
CURTAIN WALL CONTRACTOR: W & W Glass Systems
Inc., Nanuet, NY
FOUNDATION CONTRACTOR: Urban Foundation/Engineering,
East Elmhurst, NY
CONSTRUCTION MANAGER: F.J. Sciame Construction Co.
Inc., NYC
A 60-ft.-high Ferris wheel, a 4,000-sq.-ft. Barbie Dollhouse
and a 5-ton, 20-ft.-high, 34-ft.-long T-Rex may sound like
amusement park attractions, but they're not. These are all
part of the fun at the 100,000-sq.-ft. Toys 'R' Us in the
heart of Times Square.
Creating something "fun" requires a lot of hard
work. For this store it included a gut renovation of existing
space, incorporation of additional steel for its atrium, excavation
of part of the basement, removal and installation of the building
facades, threading elevators through a maze of shoring and
bracing and doing everything on a tight schedule.
The first step in this project was a gut renovation of an
original 1936 theater. Gutting including removal of existing
elevators and escalators and sloped steel and concrete. The
new retail store required the integration of over 700 tons
of steel to permit the store to have a three-story atrium
and two glass-enclosed elevators overlooking the Ferris wheel
located in the atrium.
A portion of the basement had to be excavated to provide the
store with support staff area as well as elevator machine
rooms.
The existing brick facade was removed so those new structural
butt-glazed curtain wall system and aluminum panels could
be installed. The process of removing the facade and all of
the openings in the existing steel for elevators, escalators
and stairs, required careful engineering for shoring, cutting
and installing the new steel. Behind the curtain wall, 165
scrollers were installed to allow the entire facade to act
as a billboard.
At the perimeter of the building, at the roofline, are 51
light fixtures of 1,000 watts each to illuminate the graphics
without glare.
Other project hurdles were shoring, bracing and underpinning
for the installation of new columns to accommodate the new
atrium space and the threading of nine elevators through a
maze of steel shoring and bracing. They also included a tight
schedule, which required completion in time for Thanksgiving
and a hanging scaffold for work on duct and ceilings so floor
finishes could be simultaneously worked on.
The jury recognized the unique interior and signage, noting
that the signage creates different advertising opportunities.
In addition, the jury said the project team met the challenge
of a tight schedule, opening by Thanksgiving in time for the
Christmas selling season.
|