161st Street/Yankee
Stadium Station
Development Team
OWNER: Metropolitan Transportation Authority/New
York City Transit, NYC
ARCHITECT: di Domenico + Partners, NYC
DESIGN ENGINEER: Vollmer Associates, NYC
MECHANICAL, ELECTRICAL & PLUMBING ENGINEER: Chu
& Gassman, Middlesex, NJ
ARTIST COLLABORATOR: Accounci Studio, Brooklyn, NY
ARTIST DESIGN COLABORATOR: Metropolitan Transportation
Authority Arts for Transit, NYC
GENERAL CONTRACTOR: M.A. Angeliades Inc., Long Island
City, NY
The 161st Street/Yankee Stadium station in the Bronx is
a destination point for thousands of Yankee fans every year.
As such, it is one of the most heavily used stations in New
York City transit system. And even when there is no Yankee
game, the station averages daily traffic of 25,000 people.
The $46 million rehabilitation of the stadium, as called for
by its owner, Metropolitan Transportation Authority/New York
City Transit (MTA/NYCT), included circulation improvements,
incorporation of five-ADA-complaint elevators, reconstruction
of the escalator transfer building; an increase sense of light
and air throughout and creation of a sense of station identity
within the surrounding community.
To address project issues, the project team reshaped the site
through the application of enclosures, manipulated light elements
and incorporated art in an artist/architect collaboration.
To create a sense of identity within the surrounding community
and preserve elements of its past, service areas were wrapped
in buff iron spot brick used since inception of the transit
system in 1904. In addition, public areas were glazed to the
extent possible to provide views and natural light. Furthermore,
a working relationship with the artist allowed for a complete
integration of the Arts for Transit program. By focusing on
the continuous integration of the complex's three planes,
architectural elements of the above-ground station were designed
to flow through to spaces below, while underground features
rise up into visibility at street level. Reflections of natural
light were used to fill the space during the day, while volumes
are illuminated at night to provide a visible presence within
the surrounding neighborhood.
Furthermore, a detailed phasing program that accommodated
the extended Yankee baseball season in 1996 and 1998 through
2001 was developed in order to perform the work over a four-year
period while the station remained operational.
Safety and security was also a concern for commuters. To address
this issue, elevator towers were glazed to provide maximum
light into the station complex. This heightened the perception
of security while establishing a bright and shining landmark
for he community. A new skylight and vent structure were also
constructed to permit light and air into the below ground
station mezzanine and visually unite the three design planes
- elevated, underground and street level.
In addition, commuter flow within the transfer pavilion was
framed with glass brick to further provide an open, welcoming
environment.
In an effort not to disrupt the day-to-day activities of the
station and the commuters, who use it, much of the work on
the platforms was done during 54-hour weekend General Orders
and at night under flagging supervision. To meet the project
schedule, work was performed simultaneously in many locations,
with daily crews often in excess of 70 workers. Furthermore,
it was often necessary to have second and even third work
shifts to maintain the progress and efficiency of the work.
Structural work included repair of about 50 percent of the
steel columns and numerous steel beams; repair of spalled
concrete, map cracks and water leaks throughout the interior
and exterior of the station; removal and replacement of sidewalk
sections to facilitate the underground work, including the
construction of foundations for new structures and the installation
of new property lien boxes, junction boxes, sewer and drainage
manholes and for the planting of new trees.
Structural steel work also included new frames for five elevators,
roof and floor framing for the IRT expansion area, framing
for the canopy walkway between the elevator and the IRT platform,
replacement of the IRT mezzanine hangers, valley beams for
the new platform canopy roof, stair stingers throughout the
station, extensive beam and column repairs and floor reinforcement
for increased load capacities in various mechanical rooms.
In addition, tight site logistics required equipment storage
in seven storage trailers located on the street.
The jury noted that "the project team overcame many difficult
challenges, including building near an elevated highway and
not being able to build during baseball season."
|