Mohegan Sun
Casino, Phase II
Development Team
OWNER: Mohegan Tribal Gaming Authority, Uncasville,
Conn.
DEVELOPER: Trading Cove Associates, Waterford, Conn.
THEMING DESIGN ARCHITECT: Rockwell Group Architecture
Planning and Design, NYC
STRUCTURAL ENGINEER: DeSimone Consulting Engineers,
NYC
WATER FEATURES DESIGN CONSULTANT: Cloward and Associates,
Provo, Utah
THEMING CONTRACTOR (Wombi Rock): George M. Raymond
Co., Orange, Calif.
TURTLE SHELL CONTRACTOR: Alexander Manufacturing
Inc., Portland, Ore.
CONSTRUCTION MANAGER: Perini Corp., Framingham, Mass.
One of the most important elements that attract customers
to a casino is the venue's theme. For the $50 million second
phase of the Mohegan Sun Casino in Uncasville, Conn., its
Wombi Rock, Turtle Shell and Taughannick Falls stand out as
customer attractions.
Wombi Rock is a 60-ft.-high structure with a dance floor on
its second level and a VIP bar on its second floor mezzanine
that overlooks the casino. To build this element, a universal
support was created so two 40-ft.-high arches between towering
peaks that raced up to the planetarium dome above evolve from
a three-dimensional AutoCAD file to reality.
Wombi Rock was envisioned as a glowing mountain that would
appear as natural as possible. It utilizes three types of
onyx to achieve this. One of the challenges encountered during
the construction of Wombi Rock was that the lights behind
its panels reached 120-degrees Fahrenheit, the PVB inner layer
of the composite panel would weaken and adversely affect the
structural integrity of the composite panel. The solution
to this problem was to build in some slots at some seams where
the panels come together to allow the air to circulate naturally.
While supporting the panels was one challenge, assembling
them was another. To solve this problem, a typical steel angle
frame needed to be designed to support each individual panel.
Three dimensional angle frames were prefabricated in sections
and then married into the corresponding three-dimensional
angle frame supported by the universal struts and then attached
with machine screws through pre-drilled holes.
The Turtle Shell is a three-dimensional tube frame that outlines
the shape of a turtle. Its footprint is 75-ft. by 60-ft. It
is 30-ft. high. The challenge posed with constructing this
themed element was that the architect dimensioned it in two
dimensions only - plan and elevation. But the Turtle Shell
is a complex three-dimensional shape that has structural tubes
and pipes bending about both of its axes. To complicate construction
further inlaid glass panels filled in between the steel framing.
The glass is a planar element that was supposed to fit in
the three-dimensional element. To resolve these problems,
a software program was used to illustrate the areas of conflict
between the glass configuration and geometry with the structural
steel.
Taughnnick Falls consists of two series of 45-ft.-high waterfalls
situated opposite each other in the casino's retail corridor
facing the hotel lobby entrance. Installation of two sets
of staircases and escalators from the hotel lobby to the retail
corridor had to b e coordinated with the falls too.
The challenge in constructing Taughannick Falls was taking
a three-dimensional AutoCAD design and turn it into reality.
Coordinating the location of the structural elements behind
the themed rockwork of the falls, while designing it to withstand
the water pressure, was another project challenge. The solution
was using the three-dimensional design as a tool to locate
33 pools, support walls and penetrations for plumbing. The
unique structural feature of the falls is that structure transfers
at each pool elevation. To resolve this, the walls of the
falls were offset from the final face of the rockwork to allow
the variable contouring to take place during construction.
In addition, access to the valves was required for maintenance.
The solution was a series of catwalks behind the falls and
within a cavity area above the retail space to provide access.
In its decision to recognize this project, the jury praised
the project team and noted that they offered "creative
use of interior and structural solutions to achieve their
goals."
|