Polytechnic
University's Donald F. and Mildred Topp Othmer Residence Hall
Development Team
OWNER: Polytechnic University, Brooklyn, NY
ARCHITECT: Davis Brody Bond, NYC
STRUCTURAL ENGINEER: Weidlinger Associates, NYC
MECHANICAL, ELECTRICAL & PLUMBING ENGINEER: Jaros
Baum & Bolles, NYC
GEOTECHNICAL ENGINEER: Langan Engineering and Environmental
Services, Elmwood Park, N.J. and NYC
FOUNDATION CONTRACTOR: Urban Foundation/Engineering,
East Elmhurst, NY
CURTAIN WALL & WINDOW CONTRACTOR: W & W Glass,
Nanuet, NY
CONCRETE SUPERSTRUCTURE CONTRACTOR: Northside Concrete,
Brooklyn, NY
PRECAST CONCRETE CONTRACTOR: Global Precast, Ontario,
Canada
PRECAST CONCRETE PANEL ERECTOR: Tristate Stone Erectors,
Succasunna, N.J.
CONSTRUCTION MANAGER: J.A. Jones Construction Group,
NYC
PROGRAM MANAGER: Jacobs Facilities, NYC
For universities to grow, they need to increase student
enrollment. One way Polytechnic University did this was to
build its very first dormitory, the $40 million Donald F.
and Mildred Topp Othmer Residence Hall.
The dormitory is part of a plan to attract students from all
over the country. Therefore, it was imperative that it be
completed and ready for occupancy before the start of the
fall 2002 semester. However, this target was jeopardized by
a delay in permitting before the project got under way.
The delay was caused not by the complexity of the request,
which involved only the relocating of a sewer, but by bureaucratic
snags such as the application not being expedited sufficiently
to fit the desired schedule.
In addition, the job could not begin until the sewer was moved
beyond the building footprint. The problem was resolved by
the personal intervention of Brown and Prof. F.H. (Bud) Griffis,
director of Polytechic's newly formed Center for Construction
Management Technology, who took a proactive role on the project.
Their meetings with officials of the New York City Department
of Environmental Protection cut through the red tape and quickly
secured the permit.
Although the permit was secured, the delay had already pushed
back the project start by 30 days. As a result, Brown and
Griffis moved to renegotiate the cost-plus contract with the
construction manager, J.A. Jones Construction Group of New
York, offering contractual incentives and cash bonuses to
meet major project milestones.
Incentives were to be provided, for example, to enclose the
building by January 15, 2002, a month after the date specified
in the original contract, and to have it ready for occupancy
by July 2002. The construction manager, in turn, offered incentives
to subcontractors to meet the goals. Furthermore, reliable,
timely payments, rapid turnaround on requisitions and the
establishment of a contingency fund ensured that the work
would proceed smoothly.
The entire project team, including subcontractors, was brought
in on the university's objectives of getting the project back
on track and finishing it on time or before.
Another key to delivering the project on schedule, against
all odds, was the fact that the project team had worked together
from the outset. The construction manager was involved as
early as 30 percent completion of the schematic designs -
even before the property was purchased. This helped establish
the design and minimized changes to keep costs down.
Within several months of the project's start, the 30-day delay
had been recovered and the project was moving forward rapidly.
Ground was broken for the concrete-framed, precast concrete
and glass-faced structure in December 2000, and the foundations
were completed in just 14 weeks - including the time for cost-cutting
design changes.
The construction manager established a 16-week program, with
an aggressive three-day per floor cycle, to complete the concrete
superstructure. The result was that the project was topped
out in July, ahead of schedule.
In addition, the precision of the concrete embed placement
by the superstructure contractor made it possible to accelerate
erection of the precast panels and curtain wall with minimum
welding in the field. And, the use of a four-sided structural
silicone system for the glass curtain wall system avoided
the need for a mockup, saving more time. Furthermore, the
owner arranged to use adjacent properties on the east and
west sides of the site to allow work to progress from both
sides rather than having to work from inside the building
proper.
The jury praised this project for the teamwork involved in
finding solutions to so many project challenges. It also recognized
this project for being one of the first general building projects
to offer an incentive program to the construction manager,
who in turn passed it on to the subcontractors, in order to
meet the occupancy date.
|