Random House
World Headquarters/ The Park Imperial
Development Team
OWNER & DEVELOPER: The Related Cos., NYC
OWNER: (offices): Bertlsmann/Random House Inc., NYC
ARCHITECT (core and shell): Skidmore, Owings &
Merrill, NYC
ARCHITECT (residential): Ismael Leyva Architects,
NYC
ARCHITECT: (residential): Adam D. Tihany International
Ltd., NYC
INTERIOR DESIGNER: HLW International, NYC
STRUCTURAL ENGINEER: Thornton Tomasetti Engineers,
Newark, NJ
MECHANICAL ELECTRICAL & PLUMBING ENGINEER: Cosentini
Associates, NYC
GEOTECHNICAL ENGINEER: Langan Engineering & Environmental
Services, NYC
SITE & SUBWAY ENGINEER: Vollmer Associates, NYC
STEEL ERECTOR & FABRICATOR: ADF Steel Corp.,
NYC
CONCRETE CONTRACTOR: North Side Concrete Corp., Bronx,
NY
CONCRETE SUPPLIER: Quadrozzi Concrete corp., Rockaway
Beach, NY
FOUNDATION CONTRACTOR: Urban Foundation/Engineering,
East Elmhurst, NY
HOIST & SITE PROTECTION CONTRACTOR: Atlantic
Heydt, Maspeth, NY
CONSTRUCTION MANAGER: Plaza Construction Corp., NYC
With spectacular views facing Central Park, the 675-ft.,
50-story structure on Broadway in midtown Manhattan is remarkable
in both its concept and execution of that concept.
This $180 million project is a true mixed-use project. It
features two distinct structural elements, a 25-story corporate
headquarters building for Random House that has been topped
using a cantilevered platform by a 25-story luxury condominium
tower, The Park Imperial.
Featured in its unique silhouette is a series of geometric
angles with a tall central section jutting upward between
two lower sections that, appropriately, resemble bookends.
The profile of the building follows the diagonal of Broadway
and the structure steps back twice, at the sixth story, atop
the podium base, and again at the 26th story, the base of
the residential tower. Above the 90-ft.-tall podium, the central
portion of the building steps in and out vertically, a design
that furnishes abundant surface area for the Central Park.
The project's two distinct structural elements posed the greatest
challenge for the project's team.
The office structure has a structural steel frame and the
residential portion has a concrete slab on concrete columns,
creating a 27-story foundation for a 25-story building in
the sky.
The primary structural task was to marry both frames. To achieve
this, the 26th and 27th floors have to serve as transfer floors,
where massive steel members transfer the concrete loads to
the steel structure below. Because the layout of the residential
tower is completely different from the layout of the office
tower, there is no correlation between the concrete columns
and shear walls and the steel columns below. Steel girders
pick up the loads from the columns and carry them to a maze
of trusses below. The girders, ranging in depth from 55 in.
to 87 in., span to transfer trusses that also serve as outrigger
trusses for the lateral load-resisting system. The trusses
traverse the entire floor and connect to perimeter belt trusses
that encircle the structure and help accommodate the load
transfer. Thus, the trusses do double duty by carrying both
gravity and wind loads.
As a tall and slender structure, the tower is subject to wind
movement. Solely for the comfort of its occupants, the building
features a tuned liquid column damper to limit the isolation
of the building and regulate its movement. This is the first
time a fluid mass tuned damper has been used on a structure
in the U.S.
Because of the location of the structure, foundations required
sophisticated underpinning techniques to support the adjacent
buildings on minipiles at the west side of the site. This
required drilling through water-bearing earth to rock from
underneath the buildings. On the east side of the site, subway
tunnels had to be braced under Broadway using caissons and
traditional sheeting and shoring methods. At the center of
the site, the location of the core footings, the ground inexplicably
drops off, and the rock expected close to subgrade was not
found. As a result, an additional excavation of 25 ft. to
30 ft. of excavation was required to reach sound bedrock.
The project's fast-track schedule and type of trades involved
in the project called for careful planning and a great deal
of coordination. This included bidding packages for long-lead
trades early.
The intricate logistics of the construction process were simplified
by using steel climber cranes, one of two used for steel erection,
then by the concrete contractor, and back again. The crane
was jumped at the completion of every two stories, and when
the steel framing was completed, was raised to the 27th story,
where it was slid along horizontal tracks to a position one
bay south of the footprint of the residential portion, a feat
rarely, if ever, performed on a structure in New York
Value engineering was implemented to save time and money.
The choice of steel framing for the 27th floor, at the top
of the transfer level, for example, rather than concrete beams
or steel encased in concrete, was a result of that process.
The jury praised this project, calling it "a major mixed-use
structure whose project team was challenged by site logistics,
requiring a redesigned foundation as construction progressed."
|