Bard College
Performing Arts Center
Development Team
OWNER: Bard College, Annandale-on-Hudson, NY
ARCHITECT: Gehry Partners, Santa Monica, Calif.
STRUCTURAL ENGINEER: DeSimone Consulting Engineers,
NYC
MECHANICAL, ELECTRICAL & PLUMBING ENGINEER: Cosentini
Associates, NYC
STEEL FABRICATOR (curved steel): Columbia Wire and
Iron Works of Portland, Ore
STEEL FABRICATOR (conventional steel): Berkshire
Bridge & Iron of Dalton, Mass.
STAINLESS STEEL FABRICATOR: A. Zahner Co., Kansas
City, Mo.
STEEL ERECTOR: Brownell Steel Inc. of Scotia, NY
STEEL DETAILER: Angle Detailing, Wilsonville, Ore.
CONCRETE CONTRACTOR: Darlind Construction, Lagrangeville,
NY
GEOTHERMAL DESIGN ENGINEER: RJ Dooley and Associates
Inc., Poughkeepsie, NY
THEATER CONSULTANT: Theatre Project Consultants,
Ridgefield, Conn.
ACOUSTIC CONSULTANT: Nagata Acoustics Inc., Santa
Monica, Calif.
CONSTRUCTION MANAGER: Daniel O'Connell's Sons Inc.,
Holyoke, Mass.
The fact that the Bard College Performing Arts Center in
Annandale-on-Hudson, N.Y., was designed by Frank O. Gehry
may make it a bigger attraction than some of the college's
opera, dance, theatrical or orchestra productions.
To begin with, the design incorporates curved surfaces with
two distinct surface applications. The performance theater
has curving walls around the entire perimeter, while the teaching
facility has a warped roof system. Each application posed
unique challenges, but the process by which a solution was
rendered is similar.
The genesis of each surface was developed from the architect's
physical model. Once this was achieved in physical form it
was digitized using a large armature that reads spatial coordinates
from hundreds of control points on the surface. The coordinates
are read into a software program and then meshed to form a
contiguous surface.
To achieve economy, chaotic shapes were made regular so that
each element could be fit with a structural grid work on a
10-ft. model. Support lines representing structural steel
ribs and bracing were drawn in and then exported to structural
analysis software. Once designed, accurate solid shapes and
connections could be fabricated.
The steel ribs of the performance theater extend from the
ground level up to 50 ft. to 75 ft. to the underside of the
main roof. To avoid the use spray fireproofing and epoxy paint
systems, the structural roof was cantilevered through the
auditorium walls so that the ribs could act as mullions instead.
In addition, the cantilevering removed an imposed vertical
load on the curved steel members; greatly reducing the bending
stresses.
Sequencing and the coordination of three major structural
trades also posed project complications because there were
many points of interface between the main theater's cast-in-place
concrete walls, the teaching theater's reinforced masonry
and the transition area and the envelope's structural steel.
To expedite and coordinate work, these trades performed their
tasks simultaneously.
To coordinate the entire project team and all of its work
disciplines required streamlining the communication system
using Project Talk, an Internet-based system. All of the project's
subcontractors, design team members, consultants and the construction
manager linked to a common data base to share, review, respond
and react to information.
The project's program, acoustical requirements and heating
and cooling system were also areas addressed by the development
team.
The project's program was challenging because of the multipurpose
functions of Theater 1. Each function has a different priority
that needed to be addressed within the theater. The solution
to this challenge was the project's final design.
Acoustical requirements impacted every consultant on the project,
from the detailer to the HVAC engineer. The solution was two-fold:
one was the use of concrete and the other was each consultant
developed its own solution through the design process for
different areas of the project.
Use of a geo-thermal heating and cooling system was innovative.
This system consists of 150, 500-ft. deep wells with heat
exchanger and polyethylene pipes with a U-Bend at the bottom
to provide 100 percent of the project's required heating and
cooling needs.
The jury praised the team for implementing what it called
"a difficult design" on a constrained budget and
for the project's innovative use of geo-thermal energy.
|