Austrian Cultural
Forum
Development Team
OWNER: The Republic of Austria
ARCHITECT: Atelier Raimund Abraham, NYC
STRUCTURAL, MECHANICAL, ELECTRICAL & PLUMBING ENGINEER:
Ove Arup and Partners, NYC
CURTAIN WALL CONSULTANT: R.A. Heintges Architects
Consultants, NYC
CONCRETE SUBCONTRACTOR: Slattery Skanska, Whitestone,
NY
OWNER'S REPRESENTATIVE: Hanscomb Inc., NYC
CONSTRUCTION MANAGER & GENERAL CONTRACTOR: Barney
Skanska, NYC
DEVELOPER: Bundes Immobilien Gesellshaft, Austria
The Austrian Cultural Forum is a project that was almost
never built. It began with a worldwide design competition
and selection of a winner seven years before construction
actually began.
In addition, the project had to be re-bid three times. By
the time the project was bid for the third time, the New York
construction community needed to be convinced it was worth
bidding on because they already saw it as a "problem
project."
Finally, a bid was accepted for the 22-story, 33,000-sq.-ft.
building - a building whose design mandated an articulated
sloped curtain wall, exposed architectural concrete and a
zinc metal panel wall system.
In addition, the site, located mid-block with adjacent properties
on three sides, was difficult to stage. It required careful
analysis to develop an appropriate construction sequence.
More significant was the building's 25-ft. wide by 80-ft.-deep
footprint for a 278-ft.-high building which did not allow
many options for placement of a hoist and tower crane. To
meet this challenge, a logistics plan took into account these
constraints and also factored in the means for completing
a precise architectural concrete project with a complicated
curtain wall system.
While the schedule was also key to the project, the budget
was of even greater importance. The only solution was extensive
value engineering to bring the project in at $20 million.
Value-engineered items included changing the exterior panels
for the rear and sides of the building from a powder-coat
metal to Rheinzink; a reduction in the amount of HVAC control
systems; elimination of a solar panel at the top of the building;
and less costly lobby finishes.
The building's infrastructure also posed a challenge. Elevators,
bathrooms and all vertical service requirements for the mechanical
and electrical systems had to be squeezed into the small footprint
while maximizing usable area. The need to maximize the usable
area also presented a challenge in determining the best type
of mechanical system. Space limitations led to the use a unitary
heat pump system. This eliminated the need for too many duct
risers, resulting in a pair of mains that carry both the heating
and cooling requirements for the structure. In addition, specifications
for the building's infrastructure stipulated that the heat
pumps would be located above the bathroom areas wherever possible
to prevent them from taking up floor space.
Routing of the ducts from the various units to the zones they
served was a great challenge due to space constraints. The
solution required coordination of all of the structural, mechanical,
electrical and plumbing elements in a tightly constrained
space.
The slenderness and height of the building also mandated that
the building be a concrete structure. Another interesting
structural point of interest is the building slopes 11 degrees
to meet the zoning envelope requirements and the high levels
of reinforcement and high level of high-strength concrete
required additional care and supervision on the part of the
contractor.
The jury said "every aspect of the project was a challenge
from the site to the forming of the project." They called
it a one-of-a-kind project European standards, precise tolerances
and exacting dimensions.
|