Aventis Tenat
Fitout
Development Team
OWNER: Hines Interests, NYC
ARCHITECT, MECHANICAL, ELECTRICAL & PLUMBING ENGINEER:
Kling Lindquist Partnership, Philadelphia
TENANT: Aventis Pharmaceuticals, Bridgewater, NJ
GENERAL CONTRACTOR: Turner Construction Co., Somerset,
NJ
Tenant fitouts usually take place after the core and shell
has been constructed. But for the Aventis Tenant Fitout at
200 and 400 Crossing Boulevard in Bridgewater, N.J., it took
place simultaneously during construction of the core and shell.
More specifically, the $27.7 million project involves 11 35,000-sq.-ft.
floors in two 8-story buildings. One of the two buildings
was fully fitted-out and its mirror image included three floors
for Aventis.
Construction of Building 200 began in January 2001 and Building
300 began in February 2001, with completion dates of February
2002 and March 2002 respectively.
To perform the fitout while the buildings were being constructed
required teamwork and a close working relationship with the
team members constructing two structures. It also involved
the prepurchasing of materials such as sheet metal and sprinklers,
light fixtures, doors, aluminum frames and hardware and then
storing these items onsite until the project was ready for
their installation.
The schedule also played a key role in this project's success.
For this project, the work was scheduled from the inside out.
This had to be done until there were base building core walls
around the perimeter. And while the framing for perimeter
offices were being installed, the project team used the centerline
of the space between the granite panels where window frames
had not yet been installed so accommodate the space for the
window frames.
Project team members also faced the danger of delaying interior
work because the roof was not complete because the roofing
contractor was waiting for an adjustment to the granite panels.
The project team took alignment of the granite panels to task
so the roof work could be finished and the perimeter walls
completed which in turn allowed the interior work to proceed.
Difficulties were also encountered on the eight floor of Building
200. For some reason, the installation of perimeter insulation
was held up which meant that the eighth floor fireproofing
could not be applied to the roof steel until the roof was
watertight. This placed undue stress on the ability to complete
the interior finishes on the eighth floor. The solution was
teamwork to finish the work that needed to be finished to
allow the interior work to continue.
In addition, tenant work in the elevator lobbies could not
begin until all of the elevator doorframes were installed.
This resulted in a late start on the elevator lobbies. By
working extensive overtime hours, the time lost in this situation
was made up.
One final hurdle was getting all of the subcontractors to
finish the work, as well as obtaining all of the required
final inspections, throughout the height of a holiday season.
A temporary certificate of occupancy was issued on January
2, 2002 through perseverance and teamwork.
The jury singled out this project's team's construction of
a bare wall so that it could begin the interior fitout project
simultaneously with the construction of the base buildings.
|