Hudson River
Way Pedestrian Bridge
Development Team
OWNER: Albany Department of General Services, Albany,
NY
ARCHITECT: Einhorn Yafee Prescot, Albany, NY
DESIGN ENGINEER: Clough, Harbour & Associates,
Albany, NY
LIGHTING & ELECTRICAL CONTRACTOR: Signal Ahead
Inc., Melrose, NY
PRECAST CONCRETE CONTRACTOR: Fort Miller Co. Inc.,
Schylerville, NY
ORNAMENTAL CONCRETE BLOCK CONTRACTOR: A&K Slipforming
Inc., Cobilskill, NY
ORNAMENTAL RAIL CONTRACTOR: Riverside Fab Inc., Glens
Falls, NY
FOUNDATION CONTRACTOR: J&E Pile Driving, East
Syracuse, NY
TRAFFIC CONSULTANT: Donnelly Construction Inc., Mechanicsville,
NY
GENERAL CONTRACTOR: Harrison & Burrowes Bridge
Constructors Inc., Glenmont, NY
The Hudson River Way Pedestrian Bridge project is the culmination
of an effort to reconnect modern downtown Albany and its historic
waterfront. The 650-ft.-long by 24-ft.-wide, five-span bridge
not only provides physical access, but serves as a virtual
outdoor museum to celebrate the community's historic link
to the Hudson River.
This $6.15 million bridge spans Interstate 787 Northbound
and Southbound, It also spans the tracks of the Canadian Pacific
Railroad. Included in the project is a pedestrian plaza, a
decorative concrete staircase, an elevator building, an access
ramp, drainage and streetscape improvements, engraved granite
bricks on the bridge deck, ornamental lighting and fencing
and integration of decorative elements and artwork that reflect
Albany's history.
Among the project's many challenges was accommodating archaeological
excavations in the bridge's vicinity. Archeological investigations
uncovered the remnants of the city's original wooden defensive
stockpiles near the west landing of the bridge. The project
team also found a primitive brick storm and sanitary sewer
from 1788. The discovery of these finds threatened to prolong
the construction schedule. However, due to close cooperation
between the New York State Office of Parks, Recreation and
Historic Preservation, the city's archeologist and the general
contractor, the general contractor was able to complete the
excavations sooner than expected.
Design challenges were presented by a Design Steering Committee
that was composed of local civic and business leaders. The
Design Steering Committee's recommendations were incorporated
into the design. In one instance, when the committee wanted
stone facing on the bridge's decorative elements, a design
element that would impact the project budget, an alternative
material, textured concrete, was reached.
To create a link between the outdoor museum and the waterfront
community, the bridge was lined with 30 concrete obelisks,
each featuring unique artwork created by local artists. Each
mural represents a time period in Albany's history by depicting
artifacts uncovered in nearby archaeological excavations.
Another challenge was to integrate the historic theme of the
bridge with the architecture of the surrounding modern city.
This was accomplished with the choices for forms and materials.
Landscape treatments of granite paving, black iron fencing,
period lighting fixtures and signage also contributed to the
solution for this challenge.
Finally, funding was a challenge for this project. While $3.3
million was provided in the form of state and federal aid,
it was up to the city to raise the balance from other sources.
A large portion of the funding was raised from private individuals
and corporations in the Albany area who participated in the
"Build it Brick by Brick" campaign. This campaign
resulted in the sale of 10,000 personalized granite bricks
purchased by local citizens, business organizations and civic
groups, to pave the bridge.
The jury praised the project team for "successfully integrated
an historic bridge with the architecture of the city. They
also created a museum that connected the bridge to the waterfront
community."
|