|
Hyatt Regency at South Pier
Cost: $52.5 million
Development Team
Owner: Cal harbor Urban Renewal Associates (A joint venture of Hyatt Development Corp., Chicago and Mack-Cali Realty Corp., Cranford, N.J.)
Construction Manager: AMEC, NYC
Architect: Brennan Beer Gorman/Monk, NYC
Structural Engineer: The Cantor Seinuk Group, NYC
Mechanical Engineer: Cosentini Associates, NYC
Foundation Contractor: Schiavone Construction, SEA BRIGHT, N.J.
Concrete Contractor: Forsa, Little Ferry, N.J.
Mack-Cali Realty Corp.'s dream of turning its Jersey City Harborside Financial
Center into a "City Within a City" took a significant step forward last
year with the completion of a Hyatt Regency Hotel on the south pier of the complex.
The new $52.5 million, 287,000-sq-ft., 9-story hotel is built on a 100-year-old
railroad pier. In its first-ever waterborne precast project, foundation subcontractor
Shiavone Construction created the entire 500 yds. of precast pier deck at a waterfront
casting yard in Sea Bright, N.J. Slabs that were too heavy for the firm's casting
yard crane were cast on a barge, towed to the site and then lifted into place.
Once the pier was ready, a project crane was placed on a barge on the pier's upriver
north side, and construction manager, AMEC of New York City, studied both tides
and wind patterns in order to plan the best lift times of the day.
Forsa Construction Co., the Little Ferry, N.J.-based concrete superstructure contractor,
then devised ways of delivering and pumping concrete from a barge.
Brennan Beer Gorman/Monk, the NYC-based architecture firm that designed the hotel,
had to figure out how to build it with no basement. It came up with a 5-ft.-wide
by 5-ft.-tall by 400-ft.-long concrete trough on the underside of the pier that
houses the hotel's rainwater and wastewater pipes, protecting them from freezing
temperatures, river ice and debris. The project was completed two months ahead
of schedule.
|