|
UBS Warburg Expansion
Cost: $100 million
Development
Team
Owner: UBS Warburg LLC
Project Management: Turner Construction
Co., NYC
Architect: Skidmore, Owings
& Merrill, NYC
Structural Engineer: Thornton-Tomasetti
Engineers, NYC
Mechanical, Electrical and Plumbing
Engineer: Cosentini Associates, NYC
Geotechnical Engineer: Langan
Engineering and Environmental Services PC, NYC
Telecommunications Consultant:
Walsh-Lowe & Associates, Inc., Stamford, Conn.
Excavation Contractor: Thalle
Construction Co., Briarcliff Manor, N.Y.
Steel Contractors: Berlin Steel
Construction Co., Kensington, Conn. and Cives Steel Co., Lido
Beach, N.Y.
Electrical Contractor: Belway
Electrical Contracting, Elmsford, NY
Mechanical Contractor: Harry
Grodsky & Co., Inc., Springfield, Mass.
Drywall Contractor: A&A
Drywall & Acoustics, Inc., Milford, Conn.
Foundation and Superstructure Concrete:
Tri-Star Building Corp., Pleasantville, N.Y.
Scaffolding & Hoisting Contractor:
Regional Scaffolding & Hoisting Co., Inc., Bronx, N.Y.
It's the largest trading floor in the world - 54 ft. high,
225 ft. wide and the length of two football fields - and it's
in Stamford, Conn.
The trading floor of the UBS Building is on the top floor
of an eight-story building that was originally built in 1998
as The Swiss Bank Center. A 23-month, $100 million expansion
of the building, now headquarters of UBS Warburg LLC, was
completed in May 2002.
Among other accomplishments, the makeover added another 120
ft. to the giant trading floor.
Even though some trading desks were no more than 3 ft. away
from the new construction, the expansion was done without
ever slowing the bank's operations. A temporary wall was built
at each floor to separate the bank work from the construction
work. At the tie-in location there were an operating trading
floor, a data center, offices and a parking garage.
Most of the work was done at night and on weekends. "When
a trading floor and data center are in immediate proximity,
construction preplanning is taken to a new level," said
Jeff Mattson, project superintendent for Turner Construction
Co., which provided management of the project.
With three basement levels extending 30 ft. below the water
table, Thalle Construction Co. of Briarcliff Manor, N.Y.,
which did the excavation, had to work hard to keep water out
of the hole while the new foundations were poured.
The top four floors of the building are structural steel.
Beam pockets for the steel connections at each floor were
cut into the building. Many of the connections were directly
over windows where trading floor desks were located. At every
floor, lasers were used to align the new walls, ceilings and
floors with the old ones.
The connecting shift crew worked for three months doing selective
demolition and extensive welding to allow the building to
accept the new structural steel. It required 54 connections
to the existing building plus 27 additional connections at
the curved roof. Once the connections were in place, the steel
erection for the extension, done by Berlin Steel Construction
Co. of Kensington, Conn., and Cives Steel Co. of Lido Beach,
N.Y., proceeded quickly.
The new interior of the trading floor was completed by fully
scaffolding the trading floor ceiling with a hung platform,
which was set in steps to follow the curve of the ceiling.
Open-ended walls were installed using conventional scaffolding,
which allowed the trading floor's double-access floor system
to be simultaneously installed with the ceiling.
During this phase of the process, there were 380 construction
workers on site.
Dismantling the temporary wall and scaffolding took six weeks.
|