|
Fast Track
Gantry Crane and Precast Panels
Speed up a Bridge Rebuild in N.J.
Route 46, a critical artery for
traffic flowing from New York, needed a major overhaul in
a tight timeframe.
by Natalie Keith
The
four-lane bridge where New Jersey's busy Route 46 crosses
Overpeck Creek in Bergen County was in bad shape.
More than 75 years old, corroded by rust, and deteriorating,
the bridge linking the towns of Ridgefield and Ridgefield
Park had never undergone major repairs, said Steven Manera,
program manager on the job for the New Jersey Department of
Transportation.
Under a fast-track effort, an $18 million reconstruction
of the bridge is nearly complete this spring - with traffic
pouring over the newly installed lanes since February.
The department's standard technique for such a fix would
require channeling all traffic onto two of the bridge's lanes
in order to demolish and reconstruct the two free lanes and
their underlying abutments and piers - then switching sides
to repeat the process on the other half. When the agency planned
the project under that approach, it came up with a $20 million
budget and a schedule of two to three years because for each
set of lanes, the team would need a full construction season
to rebuild the steel frame and to form, pour, and cure a new
concrete deck.
|
But Manera said local residents and community leaders consulted
about the project objected to the schedule because that stretch
of Rt. 46 is also a vital artery for traffic flowing from
the George Washington Bridge, which is 5 mi. to the east.
About 40,000 vehicles a day cross the 510-ft.-long bridge,
which carries westbound Rt. 46 traffic away from Manhattan
and funnels it to the New Jersey Turnpike, Interstate 80,
and other local roads.
"The locals understood what a 2.5-year project would
mean for them," Manera said. "They asked if we could
find an alternative."
In addition, a long work schedule would stretch the number
of days the area would suffer $19,000 in daily "road-user
costs," a transportation department-generated calculation
for the value of lost time for motorists, said Samir Shah,
the agency's project manager on the effort.
The $18 million alternative that the project team developed
met the community's challenge by cutting the schedule to less
than a year. Manera said work began last summer and is finishing
this spring because of three major choices: narrowing the
reconstruction to the deck superstructure while preserving
the abutments and piers of the existing foundation; using
massive precast concrete deck panels instead of pouring onsite;
and installing the panels by use of a gantry-crane system
that avoided additional lane closures.
The adjusted plan grew under the umbrella of the transportation
department's "Hyperbuild" initiative spearheaded
by its former commissioner, Jack Letteire, who retired after
Gov. Jon Corzine took office this year. The program aims to
reduce time spent on traditional design and construction methods
for selected projects.
"New Jersey is one of the most congested states in the
nation and our goal is to get out as quickly as possible to
minimize impact to motorists," Manera said. "The
approach is not appropriate for every project, but it is considered
on every project."
The initiative also streamlines design decisions to make
choices that limit the overall budget impact. In the case
of the Overpeck Creek Bridge, the adjusted plan ended up saving
from the original $20 million budget not because the precast
deck and gantry crane were cheaper than a traditional onsite
pour setup, but because the team found a way to repair the
existing foundations rather than demolishing them and constructing
new ones.
Indeed, the panels and gantry crane are more expensive than
an onsite pour, but they were the difference in shortening
the schedule, said Joseph Occhiogrossi, project manager for
Railroad Construction of Paterson, N.J., the general contractor.
"What we did is not a cheap solution," he added.
"But having the public inconvenienced for less time is
valuable."
Shrink 30 Months into Less Than 12
The six-span bridge crossing Overpeck Creek - a short, wide
basin that drains into the Hackensack River - was originally
a bascule drawbridge whose moving gears were deactivated in
the 1950s, and has since been locked in place, Occhiogrossi
said. It carried all Rt. 46 traffic until 1951, when an adjoining
bridge was built and eastbound lanes shifted over, leaving
the older structure for westbound traffic.
Only the older span required attention, and once the transportation
department chose a shortened timetable, it studied three prefabricated
deck systems, an option the agency had only used once before
in its history, Manera said. It chose a precast panel and
pedestal system by Fort Miller Co., of Schuylerville, N.Y.,
and selected McCormick Taylor of Philadelphia as its design
consultant.
"[By fabricating] panels offsite, the work has minimal
impact on traffic," he added.
Fort Miller cast the deck slabs and beams as one piece, and
as part of the contract, preassembled the bridge at its factory
in order to ensure that all of the pieces fit, Manera said.
The project's original bid documents anticipated use of conventional
hydraulic truck cranes, which are large enough to have required
nighttime closings of the bridge to install the precast panels
- and in turn would have required shifting westbound vehicles
onto a lane of the eastbound bridge by using temporary crossovers,
Occhiogrossi said. But Railroad determined that conventional
cranes would have been too large and heavy.
"There wasn't enough room to work on the bridge with
those cranes," Occhiogrossi said. "And it wasn't
clear the old bridge foundation would be able to support them."
The contractor also had to find a way to ensure that work
could take place 24 hours a day, seven days a week, in order
to meet the aggressive project schedule.
Railroad proposed a gantry crane system and won the job,
Occhiogrossi said. The system avoided loading the cranes directly
on the old bridge as well as any traffic crossover because
crews could work on two lanes while traffic flowed on the
other two.
Work began last summer to build the gantry-crane framework
of brackets, beams, and girders supported on one side by the
1951 bridge and on the other by the original bridge's piers,
Occhiogrossi said. After installing railroad tracks on that
framework, the two 70-ft.-wide, 40-ft.-tall, 90-ton MiJack
cranes were able to roll across the entire bridge length.
The cranes - assembled and disassembled onsite - were first
used for demolition. Nacirema Industries of Bayonne, N.J.,
used hoe rams to break the original concrete deck, with dumpsters
set on floats beneath the bridge to catch debris.
Then crews used the cranes to lift and install the precast
panels. After completing that demolition-and-installation
process on the first two lanes, the team repeated it on the
other pair.
The 42 precast panels weigh up to 70 tons each and measure
up to 9 ft. 4 in. by 93 ft. They connect to the existing piers
on 86 precast pedestals and bearings created because the new
deck system's beams are closer together than the old piers.
Some work took place at night to ensure that wideload trucks
carrying the panels did not cripple local roadways, the transportation
department's Shah said.
The project also entailed repairing cracks in the abutments
and piers, some more deteriorated than expected, both in the
water and above the surface. Ongoing tasks this spring involved
repairing a sidewalk, constructing a railing over the parapet
wall, and installing new lighting.
The project hit snags, such as heavy rain last year that
raised the water level, Shah said.
"They couldn't bring the barge in to complete the work,"
he added.
But all four lanes are back in business, and in the end,
the project will clock in at under a year.
Key Players
Owner: New Jersey Department
of Transportation
General Contractor: Railroad
Construction Co., Paterson, N.J.
Designer: McCormick Taylor,
Philadelphia
Panel Fabricator: Fort
Miller Co., Schuylerville, N.Y.
Demolition Contractor:
Nacirema Industries, Bayonne, N.J.
|