|
Special Report: New Jersey
Bridge Rebuild
The 76-Year-Old Goethals Extends
its Lifespan
by Katherine S. Robertson
A $63.2 million rehabilitation project promises a much-needed
structural upgrade for the weathered Goethals Bridge, a span
that carries 31 million vehicles each year from New York to
New Jersey over the swampy Arthur Kill.
KiSKA Construction Corp. of New York is leading the job to
mill off the 2-in. asphalt surface, repair the concrete decking,
replace all drain scuppers and joints, and rebuild the sidewalk.
The scheduled completion date is December 2006, said Frank
Gallo, program manager for the tunnels, bridges, and terminals
unit of the Port Authority of New York and New Jersey.
KiSKA won the contract in July 2003, facing a tight project
window that requires accounting for the unexpected, like late
deliveries, unfavorable weather, or equipment breakdowns.
"Whatever happens, KiSKA has to address it in that timeframe,"
Gallo said.
Work got moving right away last year with crews constructing
a platform under the bridge from which the contractors are
conducting the repair work. Gallo said the project got into
full swing this year.
One of the big challenges for the project is juggling logistics,
since the major commuter route has remained operational during
the day. The project team has to get crews, materials, and
equipment on the bridge as soon as it closes at 9.30 p.m.,
and has to button up the worksite by 5 a.m. so that regular
traffic can resume. Project sequencing calls for closing down
one side of the bridge at a time, with impacted traffic flow
directed to other crossings.
Gallo said the job is the biggest fix-up the bridge has experienced.
"We've rehabilitated the deck before, but this is the
first time we went in and did the whole thing," Gallo
said.
He said crews are milling the asphalt surface in 1,000-ft.
sections, while patching the 9-in. concrete roadway beneath
it as they go along. A typical patch is 4 to 5 in. deep and
2 to 3 in. in diameter. The team is also replacing expansion
and deflection joints, and rehabilitating or replacing the
steel network attached to those joints as needed.
Constructed in 1925 and opened in 1928, the 8,600-ft.-long,
steel-truss, cantilevered bridge connects industrial sectors
of New Jersey to Staten Island and greater New York City,
and provides a strategic link between New York's major airports
and marine ports. Its skeleton consists of steel girders set
atop arched concrete piers sunk 50 ft. below the bottom of
the channel. The piers reach a midspan height of 135 ft. above
the waterline to support the decking.
But the bridge already lags behind modern design standards
in various respects, including its 10-ft.-wide lanes that
fall short of today's 12-ft.-wide norm. It has no shoulders
for emergency access. The Goethals also doesn't have adequate
capacity for its current traffic flow, which includes functioning
as the main connector to the Howland Hook Marine Terminal,
the region's military port of embarkation in the case of a
national emergency.
To be sure, the current project isn't a cure for the corridor's
traffic problems. The Port Authority had hoped to address
that with a parallel $350 million viaduct across Arthur Kill.
But that 1998 proposal has met community opposition, and while
the players hash out which option may go forward, the work
on the Goethals has become even more critical.
The agency has done other high-profile work on the bridge
in recent years. In 2001, the Port Authority had spent close
to $19 million painting the steel below the viaducts, a job
that required the stripping down of 75 years' worth of earlier
paint work to get to the steel. Gallo said the paint layers
were very thick, sloughing off in layers. Another paint job
to strip and recoat the steel trusses above and below the
roadway had wrapped up the year before.
The purpose of the current deck repair job is to keep the
bridge in good repair for another seven to 10 years without
spending hundreds of millions on overhauling, rebuilding,
or duplicating the crossing. That provides the Port Authority
with time to conduct an environmental review, which it hopes
will ultimately result in the recommendation of a preferred
alternative.
Gallo said the possibilities run the gamut from a substantial
rehabilitation - which would involve replacement of the steel
and concrete decking, with costs in the range of $250 million
- to construction of a full-scale replacement bridge. The
previously proposed "twinning" concept - construction
of a parallel bridge to share the traffic load - could also
return to the table.
The environmental impact statement review, with the U.S.
Coast Guard as lead federal agency, kicked off in May with
a traffic count to provide a comprehensive picture of existing
flow and to create a benchmark for future projects. Overall,
the review will take roughly three years.
KEY
PLAYERS:
Owner: Port
Authority of New York and New Jersey
General Constractor: KiSKA
Construction Corporation
Structural Engineer: Modjeski
and Masters
Fire Protection Engineers:
The Burns Group
Traffic Engineering: AmerCom
Corp.
Milling:
Paoella Pro-Filing, Inc.
Paving:
InterCounty Paving Assoc. |
|