|
Steel Round Table
The Steel Institute of New
York in cooperation with New York Construction magazine convened
a panel in June to discuss the escalating costs of steel and
its impact on the New York metropolitan market. Here is a
transcription of what occurred.
Gary Higbee: When
we speak of steel price increases, we speak of volatility.
What are we really talking about in dollars and cents and
what are the factors behind the increase?
John Cross: When we talk
about pricing, we have to be careful to distinguish between
different types of steel. All steel hasn't reacted quite the
same way in the marketplace. On the structural side with wide
flange numbers, since early December 2003, we've seen about
a 40 percent increase in the mill price. That increase has
been primarily triggered by increases in scrap costs. As the
scrap price went up because of demand, we saw the mills have
no choice but to price their product based on the cost of
raw materials. During that same time, the global demand for
structural steel has increased and the paradigm has shifted
slightly, so that right now the pricing isn't so much based
on cost of raw materials today but more against the global
demand for steel. So what we see today is domestic structural
steel being about $100 a ton less than the global price for
an equivalent product.
Higbee: I
read in one of the local periodicals just last week that the
price recorded is $700 a ton for steel, or 75 percent increase.
Cross: Not for structural
shapes. That may be if you look at some products like tube
that is coming more from the sheet mills. All of your structural
materials are coming from electric arc furnaces with 90 percent
retired material. So there are increases in that level but
certainly not in the structural area.
Scott Melnick: Let me clarify
a little bit what John said. The first thing to remember is
that we're not in a shortage situation. It's not a supply
problem.
Ken Hiller: Our concrete
suppliers are claiming that the rebar has gone up substantially
more and they have to work from steel service centers. They
have claimed rebar has gone up about 20 cents a pound.
Allan Paull: We're hearing
the same thing.
Hiller: Yeah,
which is about double, 100 percent. However, in a steel building,
steel is substantially more structural steel than there is
in a concrete building. We found that the aberration in steel
seems to be dying down. In the last couple of months, I don't
think there's been a change. We're over that hump. Now, what
the future holds, I don't know. China scrap issues seem to
be dying down.
Paull: We have a number
of jobs that are in the process of going out to bid. In talking
to steel contractors and some owners, there was talk of indexing
the steel price. What we're finding is a lot of the contractors
do not want to index the steel price. They want to take the
risk. They're into risk by nature. In fact, the one job that
is talking about indexing, the owner is betting that the price
is going down. So, he wants to index to try to capture that
benefit. We're hearing the same thing, that there was a spike
and prices seem to have started to moderate and are predictable.
What we need in the market is predictable pricing and that
seems to have started to return to the marketplace. Steel,
the raw material, is about 25 percent of the whole cost of
a steel building.
Hiller:
If you took $160, which is a number that has been bandied
about here, I think that's about 7 or 8 percent of the total
cost.
Lawrence Weiss: I was going
to make that point that even a 50 percent increase in the
cost of raw material would work out to maybe a 10 percent
increase in the price for the steel for the job because the
erection and fabrication are larger factors. In my 30 years
experience, steel has been the one commodity that has remained
stable and, if anything, has gone down in price. It's been
remarkable to me how stable it's been and, of course, it's
due for some escalation over the year and I think the time
has come.
Higbee:
Alan, you mentioned not backing away from traditional pricing
methods. Has that been your experience with other clients?
Paull: No, most clients
would rather lock in the cost. They would rather shift the
risk to the contractors. This is just a unique client who's
used to taking risks and is willing to bet on the price.
Hiller:
We have a lot of public
work, and that becomes an issue. We sort of worked out a deal
with a public authority on the west coast where we are indexing.
The problem with this job is it's a public job. They're not
going to buy steel for probably six months. So that's a bit
of a gamble.
Weiss: I believe the Dormitory
Authority (of the State of New York) has at least one job
with an indexing. With the Queens Hospital project, the steel
was awarded based upon current prices with an adjustment upward
or downward.
Paull: The only problem
we saw was one contract we awarded in December that was an
issue and that one happened to be with corrugated steel sheet.
But everything else seems to be okay.
Hiller: We've
had a number of people coming back to us pleading for help.
By and large, we're trying to work that out with them. If
it's $20,000 we don't worry about it but in some cases it's
been $1 million and you're faced with a lot of negotiation.
It's not a slam dunk even though you have a firm price.
Paull: There is legislation
pending in Albany that would give relief for public jobs.
It's being pushed by the General Contractors Association in
New York. They're hopeful that the governor will sign it before
long.
Higbee: Apart
from indexing, are any other methods being practiced now?
Paull: We're hearing about
a shortage of four-inch plate. We're hearing deliveries well
into the fourth quarter.
Hiller: On
rebar as well.
Paull: We don't know exactly
what that means. Maybe a couple of gentlemen here can elaborate.
Just the four-inch, heavy stuff. The heavy plate. Plate is
primarily a function of the integrated process, not so much
the electric arc furnace process. There have been some integrated
mills that have shut down those facilities over the past several
years.
Neil Wexler: If I may add
to this, the cost of light gauge metal has gone up even more
significantly perhaps than rebar or structural steel. That
is significant because light gauge metal goes into all buildings
whether they are concrete or steel framed. And, subsequently,
at least in my practice, I've had a number of developers ask
us to design the building the old-fashioned way with structural
steel framing in lieu of a light gauge floor. This is happening
on a number of different projects, market rate facilities.
Not the high-end or affordable projects but the market rate.
Hiller: We've
had a lot of problems with steel studs and partitions, because
those are awarded pretty early. They don't come to the job.
So, a lot of those people have been caught. (to Paull) I don't
know if that's been your experience or not.
Paull: Other people in Tishman
have been working on that. I have not heard that directly.
Hiller: I
know I see lots of letters and these guys are pleading for
relief. I'm not sure how that works but it has to work somehow.
Higbee:
Jeff, Neil mentioned alternatives here and I wondered how,
with what you're experiencing, across-the-board commodity
increases are affecting that decision.
Jeff Smilow: I have a little
different perspective. On our current projects we see what
you guys have mentioned - a significant increase in steel
costs, approximately a 10 percent increase in steel price.
We're also seeing a significant increase in post-tensioning
material on our projects but not so much in the New York City
area. Clients are asking us, in the concrete projects that
have post-tensioning, to go away from post-tensioning and
go back to conventional reinforcing, even though there's a
significant increase in rebar. We're also seeing outside the
New York market, shortages in other materials like cement.
With steel, I call it the fear factor. The developers have
this fear factor from years of issues with steel and now this
problem. So they turn to us in fear. The new issue besides
cost is there's a significant reduction in suppliers. Fabricators
are going out of business. There aren't that many bidders.
When we start the early design of projects, developers ask
if we can go concrete. Sometimes we'll go through a number
of studies on using a non-traditional material for a particular
usage. But we always get back to the traditional material
at the end because leasing issues and practical issues control
the project. But what's interesting, in the overall scheme
of things, is there's been less steel projects in recent years.
There's a lot more concrete high-rise buildings and a lot
fewer suppliers. There is a big fear now with all the stadiums
coming on board in this town. The tonnages are dramatic in
those projects. The percentage of the total cost that structure
contributes to the project is much greater than the conventional
office building. So, there are big issues there, especially
when you have significant government involvement in those
projects. We're trying to get into innovative techniques for
dealing with these issues - from the designer. These techniques
have not been used traditionally in the steel design but have
been used in other trades. With curtain wall, for years, you
bring in a curtain wall supplier early on and coordinate more
closely and tailor the drawings to a specific type of curtain
wall system.
Hiller: Jeff, as far as
curtain wall is concerned, I'm sure I'll agree. Edge of slab
is one of the most
Edge of slab is difficult. One of
the big problems with this structure is that you slab the
side. And we try desperately now, on our major curtain wall
jobs, to award the curtain wall on a design assist basis because
it's a longer lead time than steel.
Paull: Curtain wall is even
worse because there's only, like, three major suppliers in
North America, so
It's not like we have five or six
firms who are willing to come into New York. With curtain
wall, there's only three.
Hiller: Yeah. That's much
worse.
Smilow: We try to bring
in a steel fabricator early. With projects that we've had
that early involvement, we've had the ability to tailor our
details to that fabricator's method of detailing and connecting.
It dramatically cuts down the delay in shop drawing, the RFI
process, et cetera. It leads to a smoother flowing job. But
all of this, of course, relates to the general problem of
cost increases because it's not just material. If you delay
a job six months, labor costs are going up at every step along
the way.
Paull: I'd like to discuss
that. We're finding more contractors want to come to New York
because we have a lot more work here than the rest of the
country. But one of the problems with steel is the predictability
of getting into shops. Why is our predictability at the shops
bad? It's because we can't predict when we're going to get
to our shop drawing phases. And why can't we get to shop drawing
phases? Because the geometry isn't set. We're now into diagrids,
we're now into building undulating. The computer programs
have gotten sophisticated enough that the designers can design
anything. They don't design boxes anymore. And it's becoming
very apparent to us that the AutoCAD just isn't sophisticated.
It doesn't work to the level of detail that's required of
fabricators. If you ask the engineers to both sides of me
here, they're not going to spend a lot of time designing beams.
If a beam is within two or three ft., they're happy. The fabricator
needs it within a 32nd of an inch. What's becoming apparent
is that there needs to a detailing effort where we would model
using an X steel system, model the geometry. That someone
would model the system, model the geometry, and hopefully
drive out 90 percent of our RFI problems.
Wexler: I couldn't agree
with this more.
Paull: I think that's cheap
money. It's cheaper than the designers doing it. The AutoCAD
is not the way to go. We should bid the documents based on
an X steel model. That makes estimating faster. It makes material
ordering faster. And I'll even argue that maybe we should
detail the jobs. On this side of the coast we don't detail
the connections. You talk to the fabricators and they know
what they're going to want to do. We know they're going to
want to use single-sided connections on beams. We know they're
going to want to bolt as much as they can. I don't see a big
problem in drawings coming out completely done.
Wexler: I agree with that
fully and let me tell you why.
Hiller: I take issue.
Wexler: Computer software
technology has reached the point where detailing is no longer
the old art of developing shop drawings from dimensions and
the like. The software has developed to a point where detailing
has become an engineering job. An engineer can very easily
detail the project with his engineers with the current software.
And the new software that is about to come in, in what's called
a 3D model. A 3D model is a single piece of software, which
is being used by engineers for design purposes, for drafting
purposes, for building department drawings and bid drawings.
The very same software is the software that's giving you the
details. If you can see it in 3D in the computer, you are
guaranteed to be able to build it and it will fit like a glove.
Let me just point out that the software is not totally available
in this form. It is being worked on.
Higbee: Both
you and Alan have talked about this thing. And I know AISC
has been a champion of electronic data interchange and works
with the software developers. But the way you're describing
it, as if it's something that's not working out.
Hiller: Well, let me just
comment. I agree with Alan, that modeling and so on is important,
but I really believe that the actual detailing needs to stay
with the fabricator, for several reasons. If you picture a
horse, the head of the horse is the detailing. The work is
the fabrication guy. I think he needs to control that. He
needs to be comfortable in doing that. In addition to that,
I think, Neil, you might have a liability issue here. Detailing
away, if you do something wrong, the fabricator's going to
own you. And there's a lot of possibility there in what you're
discussing.
Wexler: Well, I
Hiller: The final detailing.
Wexler: Our office is working
with you. All of our work is coming from developers. And the
developers have worked out this problem. And so, and as far
as having the detailers in the steel fabricator's shop, that
problem too has been solved. The current software is tailored
such that you are able to input the various builders and steel
fabricators, by their preferences, into the computer. So when
you start a project, you are able to tailor it for one steel
fabricator, or another. Imagine a three dimensional glass
box. You will be able to see, in a very short time, your building
in 3D on a glass box, with all of its features, stairs, walls,
elevators, and the rest. And if you like it, you will be able
to build it paperlessly. That's where this is going now. And
so, while we're not there yet, parts of this are already working.
Hiller: Neil, I think you're
envisioning something for the future. Right now with drawings
from the engineers and architects, there are disparities and
a lack of coordination. We've got a long way to go before
we can think of undertaking the detailing. The other factor
with detailing is you're overlooking the role of the erector.
When we get involved in the job, we spend time with the fabricator
and the detailer is telling them the way we'd like to see
the connections.
Higbee: We're
having this discussion to address steel price increases. So,
I'd like to start wrapping up here.
Hiller: Our experience,
and I think Alan will agree, is that the spike in steel is
dying. I don't think it's going to be anything like what it's
been. And people are now not indexing because they feel comfortable.
Paull: Contractors don't
want to index.
Hiller: There's a comfort
level. Hysteria has died down. Availability, except for some
heavy plate, is a non issue. Deliveries are a non issue. So
that's our opinion. We have a very big project in Chicago
that is a steel podium, a very tall high-rise, with a concrete
top. The developer is worried about what's happening with
steel and is looking at converting to concrete which is totally
wacky.
Paull: I thought concrete
has problems too.
Hiller: Concrete is cement.
That is another issue. Nobody knows what's happening with
concrete.
Weiss: More than price,
it's availability.
Hiller: At least in steel
we knew. We didn't know exactly but we knew there was a disaster,
$20 a ton. With concrete we can't even get an answer. It hasn't
quite hit New York. It's hit other parts of the country.
Paull: In Florida, I understand
the plants are only working four days a week.
Hiller: I'm told that in
New York now that if anything over 200 yards, you have to
negotiate. How does that affect the two-day cycle? I mean,
it's dead.
Wexler: If I may add something,
I find that in the New York area, particularly for mid-sized
projects, there is a lack of erectors who are willing to bid
and participate in the erection of steel buildings.
Paull: Actually, competent
erectors.
Wexler: I find that there
is a lack of such erectors.
Hiller: Well, you know
Wexler: The second point
is that often structural steel, particularly for mid-rise
buildings, benefits tremendously from a concrete floor, such
as a pre-cast concrete floor. The marriage is very beneficial
for steel buildings. I find that erectors, if they are willing
to erect a steel building of mid-size, they will have a hard
time erecting the plank floors.
Hiller: No, no, no.
Wexler: This I find to be
very consistent of my clients.
Hiller: It's impossible.
Paull: I would tend to
disagree. I found no shortage of competition.
Wexler: I admit that. I
skipped
Paull: We are such a
big player, just as Bovis is a big player in the market, so
when we go to our contractors and say, you have to bid on
a 750 ton job, it goes without saying that we need you to
bid on this if you want to bid on the 20,000 ton job. So,
we get our very big players going after these smaller jobs
because of our force in the marketplace. And I'm sure, Ken
has the exact same
Hiller: We insist that when
you have a job with plank, of course the steel erector has
to erect it all. If you don't, you'll never get the job done.
Secondly, we really insist that the steel fabricator assume
the responsibility for the planks, so it gets there on time.
It's all in one.
Paull: It's just treated
just like metal deck.
Wexler: In the last five
years or so, my office has done over 100 buildings with structural
steel and various types of floors in the New York Area. I'll
give you some examples: West Street, Dwayne Street, West Street
and 13th Street, Sullivan Street, West 19th Street, West 23rd
Street, East 112th and so forth. These are all buildings of
magnitude between 100,000 and 200,000 sq. ft. of residential
character at the top and with mixed use often community facilities,
parking, retail, and the like. By and large, the problem on
these buildings has been qualified erectors.
Smilow: Well, let me say,
from my point of view, we've done some plank jobs on steel.
The problem, again, lies with the detail. A plank detailer
never looks at the steel details. They don't see gussets,
they don't see bracing, they don't notch their plank to handle
it. So, the plank becomes a more difficult item.
Higbee: We've
run out of time so I'd like to end here. I'd like to thank
everybody for coming.
|