Features
 Current Features
 Past Features
 50th Anniversary



Cover Story - January 2004


On the MARC
Strong Foundation Supports Eighth Avenue Tower

By Tom Stabile

MARC rises 432 ft. into the city skyline, with a soaring crown accented by a flying column design.

But some of the most impressive work in the 435,000-sq.-ft. structure at 900 Eighth Ave. took place out of sight and in the structural underbelly of a classically compact Manhattan property.

Beneath this 45-story giant is a muscle grid of caisson support, concrete walls and clusters of steel bars that help the structure straddle two subway tunnels that cross through the site.

advertisement

The project schedule was tight. Excavation started in October 2002, the reinforced concrete superstructure was topped out in September and the building is slated for full occupancy this summer.

The project takes advantage of the promise in the Eighth Avenue corridor, said Joseph Moinian, chairman of the Moinian Group, the New York, N.Y.-based developer.

"When the site became available in 1999 we took the opportunity," he added. "In addition, full-block sites are very rare in New York City, especially an income producing site."

The $76 million building, designed by Frank Williams and Associates of New York, N.Y., will have 393 apartments on 37 floors; ground-floor retail; four-story, 550-car garage; and a common floor with a health club, laundry room, child care center and other amenities.

Jack Kestenbaum, project manager for HRH Construction of New York, N.Y., said it took value engineering and scheduling to keep MARC on track.

"We came up with alternatives to make sure we could get to each stage on schedule," he added.

First came careful focus on the foundation and using solutions designed by structural engineer Rosenwasser Grossman Consulting and executed by foundation contractor Civetta Cousins Joint Venture and concrete contractor Century-Maxim Construction Corp.

Demolition of an existing municipal parking garage took place before HRH arrived on the job. When HRH took over, work to support the future building's load began with a caisson design.

The Civetta Cousins team began by driving thick structural steel tubes into the bedrock on either side of the tunnels for the B and D lines of the NYC Transit Authority, which turn under the site. Next, workers excavated around the piles and anchored clusters of reinforced steel bars to the rock throughout that area. Then the entire complex was encased in concrete.

Once Civetta Cousins completed that phase, Century-Maxim erected giant concrete walls to support the foundation.

"The way the engineer designed it to accommodate that was to create large structural beams, but they were huge supporting walls that were 20 ft. or more high," said Tom Cardullo of Century-Maxim. "They allow the foundation floor to bridge over the subway without putting any load on the tunnel."

Even before the foundation work was complete, the HRH team had coordinated to get the project moving onto the next phase - locating the project crane on the southwest corner of 53rd Street and Eighth Avenue. It also scheduled the foundation work carefully to have the Civetta Cousins work first on the northern portion of the site, then continue to the southern portion while Century Maxim installed the massive concrete girders.

That strategy allowed the team to install a ground-floor slab on half of the 20,000-sq.-ft. floor plate so that staging work for the superstructure erection could begin while the rest of the foundation work continued on the southern side.

Kestenbaum said other key elements of coordinating the project included ensuring significant shoring for perimeter walls and the neighboring Roundabout Theatre, which also impacted the project schedule on matinee days.

On ongoing façade work, Newtown Masonry is handling the brick installation on upper floors, which run on masonry piers in between floor-to-ceiling window units interrupted only by panels covering the HVAC units.

Global of Canada made the precast concrete panels installed over the garage.

HRH also prioritized getting the garage ready for temporary occupancy in November by installing the hydraulic car elevators the valet firm will use.

Kestenbaum said the team has been racing to complete enclosure of the building before the cold weather sets in.

The building's studios and one- and two-bedroom apartments will have several layouts. The developer took advantage of a New York City affordable housing incentive program, including 20 percent of its units for lower- or moderate-income residents.

All units will have top-flight communications, marble bath tiles, stone kitchen floors and countertops, and high-end kitchen appliances.

The cherry on top is the crown design, said Anthony Rafaniello Sr., HRH project superintendent.

"It's very elaborate structurally, concrete-wise," he added. "From the roof it goes up 60 ft.".

Related articles:

On the MARC
Strong Foundation Supports Eighth Avenue Tower

The Helena
Silver and Green Are the Colors In Question

The Hubert
Turning a Landmark Structure into a Residential Gem

A Well-Rounded Square
An Upscale Mix of Residences Reshapes a City Block

Old Setting, New Style
SoHo 25 Reclaims Slender Strip for Residential Luxury

 

 


 Click here for past Features >>




 


Sponsors

© 2009 The McGraw-Hill Companies, Inc.
All Rights Reserved