Features
 Current Features
 Past Features
 50th Anniversary



Cover Story - November 2003


Coney Island Surprise

Hospital Project Keeps Skanska On Its Toes

By Amy S. Choi

Among challenges with a hospital project is to ensure construction does not interfere with existing operations.

The element of surprise is tricky in developments, particularly hospitals.

"It's an ongoing coordination, and because it's a functioning hospital you have to be respectful of all activity and aware of what the hospital is doing at all times," said Peter Chorman, senior vice president of Parsippany, N.J.-based Skanska USA Building Inc.

Skanska serves as construction manager for the $66 million Coney Island Hospital modernization project for the Dormitory Authority of the State of New York, which represents the Health and Hospitals Corp.

advertisement

The first phase of the modernization, which broke ground in November 2002, was a gut and rebuild of cardiac lab facilities and consolidation of the hospital's ambulatory care. Skanska recently broke ground on its second phase, a new 120,000-sq.-ft., seven-story addition. The new development will include 212 medical and surgical beds, a pediatric ambulatory care facility and a nursery.

The project is scheduled for completion in early 2005.

During the construction, Skanska must be aware of the hospital's needs and how to respond to emergencies. New York City's power outage during the summer, for example, hit as workers were pouring a concrete floor. The floor needed to be stopped immediately to provide additional ambulance access to the hospital for an anticipated increase in demand.

"We have to be flexible enough to organize and work around the hospital, and their needs can change in a flash," Chorman said.

Anthony Mele, project manager for Skanksa, said the most important thing is to keep the hospital functioning at all times. "You have to be very delicate with what you do while working with the existing hospital," he added.

Workers also had to incorporate the new facilities into the older campus. Beyond dealing with old former infrastructure and utility lines that were not recorded on the original documents and having to reroute the construction, project engineers had to handle new requirements for health-care facilities.

Depth requirements, for example, have changed, so the new addition was built with higher floor-to-floor heights, and bridges and ramps had to be built to connect the new to the old facility.

"You have to be creative with the different possibilities to come up with the solutions to get it done," Chorman said. "Once we were dealing with all the known quantities, life got a lot easier."

Related articles (Brooklyn Report):

Wild About Brooklyn
Developers See Investment Value In The Outer Borough

With Open Arms
Designing Museums To Be More Accessible

A Monumental Job
Federal Courthouse in Brooklyn Has Been Complex, Unpredictable

Jay is for Justice
New Forest City office tower will house state courts

Brighton Beach Beauties
Muss Development Puts Finishing Touches on Oceana Condomiums


 Click here for past Features >>




 


Sponsors

© 2008 The McGraw-Hill Companies, Inc.
All Rights Reserved