|
Retail in Brooklyn
Atlantic Terminal Retail
Complex Built Over Transportation Hub
By Amy S. Choi
Logistical nightmare is one way to describe the construction
of the Atlantic Terminal Retail Complex.
Not only did the developer and construction manager, Forest
City Ratner Cos., Brooklyn, N.Y., have to deal with the usual
dozens of subcontractors and consultants, but there also were
the logistics of building a 375,000-sq.-ft. retail complex
atop the largest public transportation hub in Brooklyn.
The Long Island Rail Road, nine Metropolitan Transportation
Authority subway lines and four MTA bus lines link at Atlantic
Terminal, which is also the third-largest hub in New York
City. Add to that mass of people about 1,000 construction
workers.
The $120 million, four-story center is on a 3.6-acre site
adjacent to the 400,000-sq.-ft. Atlantic Center Shopping Center
and an office tower housing the Bank of New York. The job
broke ground in February 2002 and is expected to be complete
in March, 2004.
The retail complex will be anchored by a 194,000-square-foot
Target store. Other retailers include Payless Shoesource,
Rockaway Bedding, Daffy''s and Avenue, a women''s clothing
store. These stores will join Macy''s, Pathmark, Old Navy
and Circuit City, which are already in operation at Atlantic
Center.
Forest City's construction team works under stipulations from
the MTA and LIRR, which own the site. From the beginning of
the process, the agencies had two needs: for the trains to
run safely and on schedule and for the design to suit the
terminal.
As such, the MTA and LIRR issued design guidelines via its
architect, DiDomenico & Partners LLP, New York City.
"The most difficult part of this project is trying to
construct the building over an active railway," said
Bob Sanna, executive vice president of design, development
and construction at Forest City, which is based in Brooklyn.
"There is a very limited amount of time to work. We have
to have everything at a particular location and a particular
time, with very little tolerance because the trains have to
run."
(While the terminal retail complex was going up, the Atlantic,
Culver and N/R rail lines were all also going through renovation.
There was nearly $1 billion in construction in the area.)
One of the major tasks of the construction team was to take
the existing foundations and structural steel that held up
the original railroad terminal, which was demolished in the
late 1980s, and incorporate them into the new development.
Research was done on the existing structure and survey work
in order to adapt and transfer the structure, but there were
still some surprises.
Some of the surprises lay in inaccurate documentation. The
Ives Group, Architects/Planners, Fair Lawn, N.J, for example,
was given design drawings of the subways from 1903. "These
were really helpful because in those days they drew things
to death and workers followed them," said Allen Weitzman,
partner at The Ives Group, the architect of record on the
project. "But over the years changes were made by various
New York City administrations and the information wasn't necessarily
recorded." Swanke Hayden Connell, New York City, is the
design architect, and Hardy Holzman Pfieffer Associates, New
York City, is the façade architect.
Sanna said it's not unusual for workers to find things they
don't anticipate. "When we actually got down into the
tracks, we found that some of the foundations weren't constructed
as they were in the drawings, which is often the case in some
of this railroad-related work," he added.
Still, the differences between the actual structures and the
drawings were relatively minor.
"We had the occasional hiccup, but the drawings were
fairly accurate," said Stan Wojnowski, project engineer
from Dewberry-Goodkind Inc., New York City, one of the project's
structural engineers. Canto Seinuk Group, New York City, is
the other.
Once the structures were mapped out accurately, the construction
team had to coordinate with the Transit Authority, which had
restrictions on where loads could be placed. None of the loads
from the retail structure could be transmitted and placed
above the railroad, so the inner structure of the retail complex
was essentially split in two parts.
Additionally, the engineers, who had to reuse the existing
foundations, had to adapt the foundations to make them code
compliant with new seismic regulations.
Despite the physical constraints, coordinating the needs of
the different agencies remained the most difficult aspect
of the long engineering and design process.
"There were so many entities involved in every decision,
whether it was the city of New York, the MTA, the Transit
Authority, the state of New York," Weitzman said. "Everybody
had their own agenda, and we were all trying to find a common
ground that would satisfy everybody. We literally would meet
with them once a week by phone for probably three years."
Aesthetically Speaking
The Fort Greene community that houses the new complex also
shaped the development of the property, which Forest City
took on in 1992 as a part of an urban renewal push by the
city.
The aesthetic challenge stemmed from integrating a retail
shopping mall, typically a big-box structure situated in a
parking field, into the urban environment of the historic
district of Fort Greene. The architects that worked on the
façade of the retail complex, Hardy Holzman Pfeiffer
Associates LLP, used a number of tricks to create a pedestrian-friendly
environment with a small storefront feel. They also collaborated
with DiDomenico & Partners on the architecture, materials
and streetscape.
"We agreed that there was an issue of transparency,"
said John Fontillas, senior associate at Hardy Holzman Pfeiffer.
"This is not a suburban site, it is an urban site, and
it was important to the MTA to create pedestrian walkways.
Each retailer needed windows that pedestrians could see into,
which was a big issue for retailers that weren't used to being
in an urban setting."
Target, for example, is one of the anchor tenants in the complex.
However, like many big-box retailers, its traditional exterior
design and need for display opportunities outside of the store
did not fit into the urban setting of the terminal.
"Most of these merchants are national merchants,"
Weitzman said. "New York City is not their bailiwick.
None of the traditional elements exists here, and there's
not a lot of proven data as to how to make a vertical shopping
center work."
Big-box retailers usually require blank walls for signage
and displays, but Hardy Holzman Pfeiffer wanted all facades
to have some sort of texture or relief in order to create
interest. Traditional masonry work, however, would have been
prohibitively expensive.
The architects relied on panels, contracting Artex Systems
Ltd., Ontario and Eastern Exterior Wall Systems Inc., Bethlehem,
Penn. The exterior façade was broken into panels that
could be fabricated and placed on the building, allowing the
team to control the look and texture of the panels. More importantly,
the panels allowed the team to close up the envelope of the
building quickly and safeguard the project from the external
elements and prevent any disruption of the four bus lines
that stopped in front every day.
Collaboration among the different operational elements and
organizations involved in the project proved to be difficult
but rewarding.
"It really is a testament to Forest City that they could
actually pull this off," Fontillas said. "There
were a lot of developers that tried."
Keith Itzler, assistant branch manager for Dewberry-Goodkind,
said it was important to go over and consider all points of
view. "Ultimately, everybody agreed, and we came out
with a reasonable solution," he added. "The project
has taken many metamorphoses, and we really take our hat off
to Forest City and the whole team for having the wherewithal
to take a lousy piece of property and make it into something
spectacular."
And perhaps most important: "The railroad and subways
continued to run," he said.
|
TEAM BOX:
Developer/Construction Manager:
Forest City Ratner Cos., Brooklyn, N.Y.
Architect/Planners:
The Ives Group, Architects/Planners, Fair Lawn, N.J.;
Swanke Hayden Connell Architects, New York City
Façade Architects: Hardy
Holzman Pfeiffer Associates LLP, New York City
Civil Engineer: Kravchenko
& Associates, E. Northport, N.Y.
Structural Engineers: Dewberry-Goodkind
Inc., New York City; Cantor Seinuk Group Inc., New York
City
MEP Engineers:
Cosentini Associates, New York City
Landscape Architect: Abel
Bainnson Butz LLP, New York City
Steel Contractors:
Empire City Iron Works, Long Island City, NY; Interstate
Iron Works, Whitehouse, N.J.
Exterior Panel Contractors:
Eastern Exterior Wall Systems, Inc., Bethlehem, Penn.,
Artex Systems, Ontario.
Plumbing and Heating Contractor:
Almar Plumbing and Heating, South Ozone Park, N.Y.
|
|