Revitalized
Downtown Renewal Spreads From
Ground Zero
by James Murdock
| Ground Zero, once a war zone, is now
the epicenter for rejuvenation throughout Lower Manhattan
and the collaborative spirit forged in the afternoon hours
of Sept. 11, 2001, remains strong as construction teams
rebuild on and around the World Trade Center site. |
Foundation work on 7 World Trade Center, the first structure
bearing the Trade Center name to be rebuilt, finished in July.
Tishman Realty & Construction Co., the general contractor,
expects to complete the concrete vaults for a Con Ed substation
by October and will begin steel erection soon after. The electrical
plant occupies the first four stories of the 52-story tower.
The building was designed to exceed New York Citys current
building and life safety codes. Its core, for example, will
be encased in concrete.
Mike Goldberg, Tishmans senior project manager, anticipates
that vertical construction on 7 WTC will advance at the rate
of one floor per week. The pace will be determined by how
long it takes to pour and set reinforced concrete shear walls.
To boost efficiency and alleviate pressure from tight site
constraints, PERI Formwork Systems Inc. custom-designed a
climbing form system that will lift itself up the buildings
sides.
Across the street from 7 WTC, work on the restoration of the
31-story Verizon Building, another Tishman project, is nearing
completion. Located at 140 West St., it is Lower Manhattans
main telephone exchange. The historic landmark opened during
the 1920s.
The majority of damage to the Verizon Building occurred as
a result of a 60-ft.-tall pile of rubble that pushed against
it when 7 WTC collapsed. In addition to shearing off roughly
25 percent of the buildings east facade, lateral pressure
from the debris damaged foundation walls and two important
structural columns.
To replace the 35-ft.-long columns, which weighed 530 lbs.
per lin. ft., Tishman used a hydraulic lift to jack the entire
building roughly one-eighth of an inch. After this work was
complete in mid-2002, Tishman repaired the foundation walls
as well as concrete floor slabs damaged when steel girders
pierced the building during the collapse of 1 World Trade
Center.
Before 140 West St. reopens in November, remaining jobs include
restoring permanent electrical services (temporary generators
have been in place since Sept. 2001) and putting the finishing
touches on the Art Deco facade and lobby. The historical restoration,
which required approval from the citys landmarks commission,
will likely represent a significant portion of Verizons
anticipated $1.4 billion bill.
Using historic photographs, Petrillo Stone Corp. is recreating
intricately carved limestone relief work while Excalibur Bronze
Sculpture Foundry Inc. is casting new bronze panels for the
facade.
"The entablature has little snakes, serpents and frogs,"
said John Turco, project manager for William Collins AIA Architects,
LLP, which is overseeing the design with Merritt Engineering
Consultant, PC. "Its beautiful, but you cant
see it because its pretty high up."
The job as a whole, however, will not go unnoticed. "On
Sept. 12, 2001, getting the phone company building back up
and running again was of utmost importance," said Fred
Corrado, first vice president of Tishman. "For those
people that have been there for two years now, seeing it up
and running will be a very emotional time."
On the Right PATH
The construction of a temporary World Trade Center station
for PATH trains to New Jersey is also nearing completion.
It reached a symbolic milestone when two structural supports
for the entrance canopy were erected in May. The 60-ft.-tall
painted tubular steel columns were the first vertical structures
to rise where the Twin Towers once stood.
Eight stories below grade, track work is complete and the
Port Authority of New York and New Jersey began testing trains
in June. In addition to making extensive trial runs and tweaking
signals before the station opens in November, remaining jobs
include readying the stations public areas for commuters.
Tammy Hileman, president of T+M Architectural Metal + Glass
Inc., said the demanding design-build schedule necessitated
complete cooperation among subcontractors. Her firm installed
stainless steel, aluminum and glass panels around the elevator
entrances and in stairwells. It worked closely with Schindler
Corp., which simultaneously installed and tested the elevators.
Although a painter died at the PATH station project in June
it was the first fatality at Ground Zero during recovery,
cleanup and reconstruction combined Hileman said she
was impressed by the Port Authoritys extensive safety
precautions to guard against the hazards of different construction
teams working in such close quarters.
One block east of the Trade Center site, the Metropolitan
Transportation Authority has begun the planning and engineering
phase for the Fulton Street Transit Center. Construction on
the $750 million project is slated to begin by 2005.
The new hub will connect 12 subway lines, relieve platform
overcrowding and provide station access for the disabled.
Two stops south on the 1 and 9 lines, the MTA has also begun
planning and engineering for a $400 million reconfiguration
and expansion of the South Ferry Terminal. Construction will
run simultaneously with work on the Fulton Street Transit
Center. Both jobs are part of a federally funded $4.5 billion
overhaul of Lower Manhattans public transit infrastructure
and are targeted for completion in 2007.
Several other projects surrounding the Trade Center site are
also in various stages of construction.
VJB Construction Corp. is readying work on 90 West St., a
340,000-sq.-ft. building south of where 2 World Trade Center
once stood. Badly damaged by falling debris, the 100-year-old
former office block will be restored and converted into apartments.
Bovis Lend Lease Inc. completed restorations on the Millenium
Hilton at 55 Church St. Work on the $32 million project began
immediately after the disaster, when construction crews sealed
off the building from weather damage. The project wrapped
up in May.
Compared to other buildings that surround the Trade Center
site, the 56-story hotel sustained relatively minor damage
on Sept. 11, which Paul Taylor, a managing partner of Stonehill
& Taylor Architects, the architect of record, attributed
to the buildings robust concrete frame.
But while the hotel escaped structural damage, roughly 1,300
windows in its all-glass curtain wall were either blown out
during the Twin Towers collapse or intentionally smashed
afterwards to lessen the hazard of falling shards. The main
entrance and plaza were also destroyed, giving Taylor the
chance to design a new entry that meets current codes for
disabled access.
Inside the 561-room hotel, virtually every surface was blanketed
by several inches of dust, which allowed Taylor, as well as
architects at Brennan Beer Gorman Monk/Interiors and Arnold
Syrop Associates, to update the buildings 12-year-old
decor. "The entire interior was stripped, and all the
air-conditioning systems were replaced," Taylor said.
"We basically used the shell of the building and rebuilt
it."
Onward, Eastward
Revitalization is radiating from Ground Zero throughout downtown,
and many new projects are helping foster a true 24-hour neighborhood
in which people can live, work and play.
Three blocks east of the Trade Center, Kreisler Borg Florman
Construction Co. is building a 287-unit apartment building
at 10 Liberty St.
Foundation work on the 45-story tower began in July 2002.
Given the sites hydrogeology, construction crews were
surprised that soil three stories below grade was not as wet
as they expected perhaps a result of massive dewatering
operations at the nearby Trade Center site, said Stephen Griswold,
vice president of Kreisler Borg Florman.
Although the soil was dry, contractors lined foundation walls
with a waterproof membrane manufactured by Grace Construction
Products, a division of W.R Grace & Co. For the supports,
it sank 640 steel pipe piles measuring 10 in. in diameter.
Work was slowed by the need to construct a steel bracing system
to support a tunnel for the 2 and 3 subway lines.
Designed by the Stephen B. Jacobs Group, PC, the building
looks like a brick and limestone transplant from Manhattans
Upper East Side. Tucked behind it on Cedar Street will be
an outdoor garden, a "signature" element associated
with the apartment manager Glenwood Management Corp. and unique
for housing in this part of downtown.
With foundation work complete, steel framing and concrete
floor decks were rising at a rate of 1.5 stories each day
in July. Like 7 WTC, the tower will have a concrete-encased
core.
To speed construction, Kreisler Borg Florman is using a hydraulic
crane manufactured by Favelle Favco Cranes USA Inc. that climbs
the building, disassembling and reassembling itself as it
goes.
The building is due to deliver in first quarter 2004.
|
Spaces for Reflection
| It mirrored
the whole volunteer spirit that was awakened during
the relief effort... |
Many of the contractors at the World Trade Center have
been on site since Sept. 11, 2001, first during the
recovery and cleanup and now during the rebuilding.
Witnessing the unfolding events has left powerful memories.
To help volunteers and construction crews affected by
the tragedy, Lisa Orloff, a volunteer who joined the
relief effort that September, founded the nonprofit
organization called September Space. In addition to
providing a place for people to meet and talk about
their experiences, it offers what Orloff described as
"alternatives" to conventional psychology
services.
They include acupuncture, massage, art classes and journal
writing sessions.
"We are an open community and we really allow our
participants to guide us in the programs we offer,"
she said.
September Space had occupied a temporary suite on the
20th floor of 520 8th Ave. until this summer when Newmark
Realty donated a permanent space on the buildings
11th floor.
To make the space ready for occupancy, the construction
industry cam through with $300,000 of labor and materials.
MKG Construction, Syska Hennessy, Component Assembly
Systems, Shaw Carpeting, Forest Electric, Heritage Sheet
Metal, The Sheet Metal Apprentice Union, EMCOR, architect
Deborah Berke and Home Depot of Staten Island donated
their design expertise, materials and labor.
After a solid month of construction, September Space
moved into its new place in July. "It mirrored
the whole volunteer spirit that was awakened during
the relief effort," Orloff said.
All are invited to see the construction communitys
generosity by visiting September Spaces new location
on the 11th floor at 520 Eighth Avenue. September Space
welcomes anyone affected by the 9/11 disaster, and acknowledges
its volunteer roots by supporting all dedicated, community
volunteers who need a gateway to services available
from a multitude of organizations and institutions.
For more information on September Space or their Iron
Skillet Cook Off event to held Nov. 3 please log on
to www.septemberspace.org or call 212-563-7570.
|
Work on another apartment complex, which will occupy both
sides of Front Street between Peck Slip and Beekman Street,
began this month. Comprising 11 historic structures, many
200 years old, and three all-new buildings, the 148,000-sq.-ft.
development will contain 96 apartments, retail space and a
maritime cultural center. The developers, a joint venture
between Sciame Development Inc., Zuberry Associates and the
Durst Organization, purchased the property from the citys
Economic Development Corp.
Development costs are being defrayed by a $48 million Liberty
Bond issued by the states Housing Finance Agency. The
bond program was created after Sept. 11 to help rejuvenate
Lower Manhattan, and Front Street represents its first application
in a low-density, historic landmark setting.
"Ive never seen such cooperation on a project as
this one," said Frank Sciame, CEO of Sciame Development
and Sciame Construction Co., the projects general contractor.
"We had complete support from the city and state. It
validated beyond any doubt that the city and state are resolved
to make sure that Lower Manhattan is rebuilt and redeveloped
as quickly as possible."
From a construction standpoint, the development will pose
several challenges. Front Streets historic buildings,
like many in the neighborhood, were constructed on timber
cribbing and piles sunk into loose fill in the East River.
"Part of the charm of the area is that the buildings
lean on each other for support," Sciame said.
To lessen the risk of disturbing adjacent structures, contractors
will drill minipiles for the new buildings foundations
and monitor the work with seismic detectors.
Sciame will also keep the buildings leaning on each other
to retain their historic integrity. It will stabilize and
preserve the existing brick facades, rather than reconstruct
them.
"Were not trying to restore the masonry to a Disneyland-like
look," Sciame said. "We want it to be authentic.
We will leave the stains, we want it to have patina."
History is everywhere on the site, added Richard Cook, a partner
of Cook + Fox Architects LLP (formerly Richard Cook &
Associates). Before Ellis Island, before the infill and development
of Lower Manhattans west side--where the World Trade
Center eventually rose--this site was where all immigration
and trade occurred in New York. It is an incredibly important
block in that the remaining structures really are this fragment
from the boom times in the early 19th century," he said.
"The buildings have a beautiful, individual personality
and we hope that the final project will reflect that."
While most public attention over the last two years has been
on the efforts to rebuild the World Trade Center, that is
only part of the story. The reconstructionand improvementof
downtown is proceeding rapidly and will supply the regions
construction industry with work, and a grand mission, for
years to come.
|
Quality of Life Initiatives
|
LMDC
Implements
$50 million
in short-term capital
projects
|
The Lower Manhattan Development Corporation is implementing
approximately $50 million in short-term capital projects
that will improve accessibility and enhance the quality-of-life
in and around Lower Manhattan. Most of the short-term
projects, which were identified with the help of the
Mayor's office and business and community leaders will
be completed by years end, and all by spring,
2004.
At the Governor's direction, the Empire State Development
Corporation will also fund a new, three-point-plan targeted
directly to helping tourism and small businesses in
Lower Manhattan.
I want to thank Mayor Bloomberg and the many business
and community leaders who played vital roles in identifying
which projects should be pursued most aggressively to
ensure Lower Manhattan continues on the track to revitalization,
Governor Pataki said. We must make navigating
Lower Manhattan easier, and improve the aesthetics in
the area as we continue to normalize conditions for
workers, residents and visitors.
Improving Access
The completion of the following projects will make it
easier to navigate the World Trade Center site as Lower
Manhattan is rebuilt:
- A bridge will be built
reconnecting the World Financial Center and Battery
Park City with the rest of Lower Manhattan;
- The Liberty Street walkway and
bridge will be upgraded, and a covered walkway on
Liberty and Church Streets will be provided.
Quality-of-Life Enhancements
The Governor has called on the LMDC to undertake a number
of initiatives to make the Lower Manhattan community
a better place to live, work and visit. Mayor Bloomberg
shares that vision. Some projects include:
- Funding $10 million in
enhancements to open spaces throughout Lower Manhattan
- in Chinatown, the Lower East Side, Tribeca, and
elsewhere, creating a network of parks and recreational
spaces in communities where they are in short supply;
- Funding an additional $4 million
to Downtown Alliance's Streetscape program to finish
transforming Broadway -- from Bowling Green to City
Hall -- into a grand boulevard with new landmark gray
sidewalks, granite curbs with street names etched
in corners, black granite strips denoting each of
the 200 ticker tape parades, and new custom design
lighting fixtures and bollards;
- Reopening the Greenmarket at
a temporary location this summer on Broadway in Liberty
Park Plaza;
- Finding ways to maintain the
security around the New York Stock Exchange, while
also beautifying the area and improving access;
- Replacing the black shroud
over the Deutsche Bank building with a mural trumpeting
a new symbol to rise at ground zero "the 1,776-foot
Freedom Tower; and,
- Contributing up to $3 million
toward the Millennium High School for 250 9th and
10th graders at 75 Broad Street, and challenging potential
private sector contributors to do their part. The
LMDC contribution will ensure Millennium High School
will open this September.
These are only a fraction of
the improvements that will occur in Lower Manhattan over
the next several months. Taken together, they will help
convince businesses and residents to remain downtown while
New Yorkers work hard to realize the long-term vision
of rebuilding and revitalizing Lower Manhattan. |
|