On the Waterfront:
Temporary Outboard Roadway
Key to FDR Drive Rehabilitation
by Jason Feldman
The Franklin Delano Roosevelt Drive, known to most New Yorkers
as "the FDR Drive," was built when its namesake
sat in the White House.
It was constructed as part of the New Deal's Works Projects
Administration, created primarily to give work to the unemployed.
World War II - and a steel shortage - came along as it was
being built.
No wonder the FDR needs some work.
"It was primarily constructed of reinforced concrete
with some use of steel on the east line columns, said Neil
Porto, associate and senior project manager for Daniel Frankfurt
Engineers and Architects, the project's New York-based design
engineer. "The concrete shows deterioration. In some
cases, timber and steel are being used to shore up columns.
There is extensive leakage, and it's top heavy so it is seismically
deficient.
"The roadway is severely deteriorated. It has lost about
80 percent of its structural capacity, and express buses are
no longer allowed on the roadway. The program is to get the
FDR Drive back to HS-20." Under the auspices of the New
York State Department of Transportation, work began late last
year on a $138 million project to reconstruct the FDR from
54th to 63rd streets.
Preventing Hemorrhage
Despite its age and decrepitude, the FDR Drive, running along
the East River from Harlem to the southern tip of Manhattan,
is one of the city's major traffic arteries.
It connects to the Bronx and Queens through the Triborough
Bridge in the north, to Brooklyn at the Brooklyn-Battery Tunnel
in the south, and provides numerous points of access to Manhattan's
East Side as well as to every one the city's East River bridges.
About 130,000 vehicles travel it everyday.
Closing the drive while reconstructing it was not an option.
Even shutting some lanes while working on them, as is traditionally
done, would have resulted in a traffic nightmare.
The solution has been the construction of a temporary outboard
detour roadway and fendering system in the East River. Once
the detour is in place, the construction team will be able
to close sections of the old highway without interrupting
traffic flow. Additional benefits include a faster schedule
and a reduction in night work.
The outboard roadway has three segments:
- An elevated structure, to be constructed over the East River
from East 53rd Street to East 59th Street.
- An elevated structure that serves as the exit to East 61st
Street for the Northbound Roadway. The 61st Street exit is
critical for traffic flow to the Queensborough Bridge.
- An at-grade portion from East 59th Street to East 64th Street.
The outboard roadway will be supported on 60- to 100-ft.-long
caissons socketed to rock. A precast concrete deck will be
placed on top of the caissons. Drilling the 64 caissons was
difficult, said David Vosseller, project manager of Cranford,
N.J.-based Weeks Marine Inc., the project's marine contractor
in a joint venture with Whitestone, N.Y.-based Slattery Skanska.
"The rock slopes 45 degrees, which made it tough to ensure
the shaft location during the drilling," Vosseller said.
The river's current also played havoc with shaft location.
"The typical flow of the river is 3.5 knots; if you throw
piece of wood into the river you would have to run to keep
pace with it," Vosseller added.
To combat the sloping rock and keep a level platform during
the drilling, the drilling platform was set up on hydraulic
jacks. As soon as the platform was level, bores were drilled
anywhere from 30 ft. to 80 ft. down to bedrock.
A temporary caisson was then lowered to the rock and filled
up to 10 ft. with concrete. "If the roadway were a permanent
structure the whole shaft would have been filled," Vosseller
said.
Placed on top of the caissons will be an 1,800-ft.-long composite
steel superstructure with a precast concrete deck, said Jason
Stern, project manager for Earthtech TAMS Consultants Inc.,
the New York-based consulting engineer for the outboard detour
roadway.
"We chose steel because it was the most economical solution,"
he added. "Precast was chosen because it was the fastest
to place and it gives us better quality. In addition, the
precast roadway eliminates the chance that loose concrete
will fall into the water. The concrete deck will be overlaid
with 1.5 in. of asphalt."
Protecting the Outboard Roadway
Because the outboard detour roadway will be built in the East
River, there was concern about wayward vessels striking the
roadway. To alleviate the risk, a fendering system will be
constructed that will deflect ships away from the roadway.
The fendering system will consist of 13 18-ft. by 20-ft. by
20-ft. structures called dolphins. "They are basically
a two-story building that will be secured by four rock anchors
and chains," Vosseller said.
The rock anchors consist of 17-in. H-piles that are drilled
straight into bedrock and connected to chains. Connected to
the dolphins will be a 250-ft.-long, 10-ft.-diameter pipe
with bracing inside.
Vosseller said connecting the chains in the current was difficult.
"We have six divers attaching the chains to the dolphins
and the rock anchors," he added.
Each link of the chain weighs nine tons.
The Start of Something Big
After the outboard detour roadway is complete by April, northbound
traffic will be diverted to the detour and work will begin
on the Southbound Viaduct Structure. The Southbound Viaduct
Structure consists of a 27-in.-thick reinforced concrete slab
supported on the west side by a massive concrete retaining
wall.
On the east side, longitudinal edge girders support the slab;
the majority of the columns are reinforced concrete. The east
girders are supported on pairs of slender steel-riveted steel
columns spaced 45 ft. on center. The columns extend down to
concrete piers at the lower level, which are supported on
piles or rock.
This structure will have to be removed with the not-inconsiderable
task of chopping through 27 in. of reinforced concrete, said
Jerome Daraio, senior project manager for Slattery Skanska.
Daraio said that during the removal stage, a shield will be
placed under the structure to ensure safety.
The replacement structure will consist of longitudinal steel
stringers supporting a standard New York State Department
of Transportation concrete deck. Design engineer Porto said
the deck will provide better performance and will be more
easily maintained.
During this period, the roof deck will also be rehabilitated.
While the roof deck is being rehabilitated, parks on 56th,
57th and 58th streets will be rebuilt. This work is scheduled
to last 21 months.
Afterwards, traffic will be detoured through the new southbound
roadway while work will begin on the northbound section. This
eight-month job includes the removal of the protective shield
over the roadway; new drainage and lighting; repair and seismic
retrofit of walls, roof and columns; construction of a new
barrier; and paving.
When that part of the job wraps up, traffic will be placed
back on the northbound roadway and the $40 million temporary
detour roadway will be removed.
"Without that roadway, it would have been a 12-year job
instead of five years," Dario said.
|