Highway and Bridge Round-up
Contractors Steer Clear
of Delaying Traffic
by James Murdock
It seems as though every road, bridge and tunnel in the metropolitan
New York area is under construction this summer.
But to the credit of engineers and contractors, any congestion
that drivers encounter is likely to be routine. That means,
despite the roadwork, few travel lanes will be surrendered.
To ensure that traffic does flow normally, construction teams
throughout the region have developed some creative solutions.
Triborough Bridge
In a 16-year project that began in 1997 and will cost more
than $1 billion, the Metropolitan Transportation Authority
is reconstructing all three portions of the Triborough Bridge.
It is the largest repair job since the structure opened in
1936 and the single largest rehabilitation that the MTA has
ever undertaken.
During the current phase, a $144 million project that began
in December 2000 and will be completed in March, a 60/40 venture
between American Bridge Co. and Koch Skanska is replacing
all 368 suspender ropes and roadway decks on the East River
span, as well as widening and replacing decks on the Queens
Viaduct.
"By the time we finish the job, the whole bridge will
be entirely new, except that you can't see that because we're
working lane by lane," said Kwadwo Osei-Akoto, the project
manager at American Bridge. "The whole objective is to
make sure that we place as minimal restrictions on the traffic
as possible."
With 166,000 motorists traveling over the bridge each day,
the job isn't easy. To avoid closing lanes on the 2,724-ft.-long
East River span, where the existing concrete decking is being
replaced with steel orthotropic panels, American Bridge commissioned
custom-designed overhead cranes.
Manufactured by Demag Cranes & Components, the Ohio-based
subsidiary of SMS Demag AG, the $3 million system is a souped-up
version of cranes commonly found inside factories. Resting
on the bridge's structural supports, three cranes hang over
the roadway and hoist panels into place while allowing traffic
to pass unobstructed. "We spent a lot of money on the
crane initially, but it pays for itself because it's safer
and very efficient," Osei-Akoto said.
On the Queens Viaduct, American Bridge is replacing the existing
concrete deck with new concrete panels. Instead of the high-tech
Demag cranes, it is using two 3000-W crawler cranes. "You
can hardly get them anymore," Osei-Akoto said. ,"We
found these in Alabama and they are at least 50 years old,
but we needed something that was narrow because of the lane
restrictions."
Garden State Parkway
Site restrictions are also the buzz along the Garden State
Parkway in Middlesex County, N.J. General contractor PKF Mark
III Inc. has just 10 to 12 in. of buffer zone between the
existing Driscoll Bridge, which carries 260,000 vehicles a
day, and a new span it is constructing.
And because of fish spawns in the Raritan River, PFK can only
work in the water during summer months.
There will be a lot of water work this summer. Rather than
damming the river to drive piles for structural supports,
PFK is drilling foundation holes from a floating barge through
60 to 70 ft. of water. The technique - an increasingly common
method called drilled-shaft construction - uses a reverse-circulation
drill to bore cavities into the bedrock: in this case, 52
shafts that are 19 ft. deep and 6 ft. in diameter.
"It's very efficient," said Pete Getchell, president
of Pennsylvania-based PFK. "You're working on top of
the water all the time so you don't have to build coffer dams,
you don't have to excavate and you don't have to dewater."
PFK was awarded the $84.4 million contract to build the new
4,380-ft. span last fall. It was subsequently awarded a $22.3
million contract to realign and widen approach ramps to the
existing bridge.
Rob Fischer, construction manager for the New Jersey Highway
Authority (which recently merged with the New Jersey Turnpike
Authority), said that since the Driscoll Bridge opened 50
years ago, its traffic capacity has been increased by narrowing
existing lanes and eliminating shoulders.
Still, the bridge is one lane short in each direction compared
to the rest of the Garden State Parkway. "It's an effective
bottleneck," Fischer said.
After the new bridge is complete, the existing structure will
be resurfaced and then reopen to accommodate only northbound
traffic. With both bridges open, the Garden State Parkway
will finally boast seven lanes and shoulders in each direction.
The project is scheduled for completion in October 2006.
Route 18
Slattery Skanska Inc. appears to have caught a break in its
$75.9 million job to extend Route 18 through Rutgers University:
Between June 1 and Aug. 15 this summer, the main campus road,
Metlars Lane, is closed to allow construction of the ramps,
loops and traffic circles that will link it to the new parallel
route.
But appearances can be deceptive. The construction team needs
as much time as it can get due to a long list of project constraints,
including close proximity to residential areas, fish spawns
in Metlars Brook and the remains of a British fort that dates
from the Revolutionary War. If archeological artifacts are
unearthed, construction must cease for 30 days.
Architectural finishes within the project will also require
extra time and attention. Slattery Skanska is constructing
six bridges out of stained concrete, for example, and will
then paint the structures by hand to resemble rough-cut natural
stone. Building with real stone would require more long-term
maintenance and is more expensive.
Work on the project began in July 2002 and has already been
slowed by the harsh winter and wet spring.
Despite these and other hurdles, the project is on target
to deliver by its September 2004 deadline. Robert Marlow,
the senior project manager at Slattery Skanska, said that
the first and most important phase should be completed this
fall. More than 60 percent of the entire job, it includes
constructing four of the six continuous-span bridges over
existing roads and Metlars Brook.
Whitestone Expressway
One project that will no doubt attract serious attention in
coming years is the replacement of the northbound Whitestone
Expressway Bridge over the Flushing River in Queens. The New
York State Department of Transportation awarded a $177 million
contract to a joint venture between Tully Construction Corp.
and AJ Pegno Construction Corp. in January.
The current structure, built in 1937, is a drawbridge that
handles more than 85,000 vehicles each day. It will be replaced
with a continuous span made of high-performance steel tub
girders. Rated grade 485, the steel will resist corrosion
and require less maintenance.
"This is the first bridge in the city to use it,"
said John Elias, the engineer-in-charge of the project at
the New York State Department of Transportation. But do not
look for all bridges to follow suit. "It's durable steel,
but it's costly," Elias added.
To maintain all travel lanes during the job, a temporary span
will also be constructed over the river. Additional project
phases entail rehabilitating the Whitestone Expressway at
grade level between Linden Place and 3rd Avenue, constructing
a new ramp from the northbound Van Wyck Expressway to the
northbound Whitestone expressway and rehabilitating the southbound
Whitestone Expressway ramp to the southbound Van Wyck Expressway.
Preparatory work on the site, which includes driving roughly
3,800 pilings, will be completed this summer. The entire project
will deliver in August 2006. There is a $2.5 million incentive
to finish early.
Brooklyn-Battery Tunnel
Another project just getting started is the four-year, $65
million rehabilitation of the Brooklyn-Battery Tunnel. The
joint venture between Tully and Grace Industries Inc. is repairing
roadway slabs in both tubes for the MTA, bringing fire lines
up to code, installing new drainage systems, fixing leaks
and replacing broken tiles.
The project's initial stage, which began this spring, consists
of cleaning air ducts to remove soot from automobile exhaust
and dust from the Twin Towers' collapse on Sept. 11, 2001.
Ensuring that traffic is not impacted will be a serious challenge
given that this project involves a tunnel. Timing is everything.
Each night, one tube will be closed for work and traffic will
be diverted into the other tube.
"The contractor has basically eight hours to do the work,"
said Yalcin Tarhan, vice president and project manager for
Parsons Brinckerhoff Inc., the design engineer. "Scheduling
the right amount of work - and that includes pouring the concrete
and allowing the right amount of time for it to cure - will
be the most challenging aspect."
Brooklyn-Queens Expressway
Two of the region's biggest jobs are finally nearing completion.
After three years, Slattery Skanksa is within striking distance
of finishing work on the Brooklyn-Queens Expressway.
The $228.8 million contract includes reconstructing 2 mi.
between the Broadway exit and 25th Avenue in Queens and reconstructing
the Grand Central Parkway connector ramp.
Peter Franco, the project manager at Slattery Skanska, said
the remaining phases entail building the new Grand Central
connector ramp and finishing work on the BQE span over Northern
Boulevard.
NYSDOT will likely add two small contracts for granite artwork
and sound walls to be installed at the eastbound Grand Central
connector, which Slattery Skanska will assimilate into the
project's final phase, due to deliver in March.
Long Island Expressway
The reconstruction of an interchange between the Long Island
Expressway and the Cross Island Parkway is another project
that is nearly complete. After three years of construction,
all ramps should be opened by this month.
The job's remaining tasks are cosmetic - removing temporary
barriers, digging drainage ditches and restriping pavement
- and involve landscaping.
The landscaping is a big item. Of the project's entire $130
million budget, $40 million is devoted to restoring environmentally
sensitive areas and building nature trails in parkland that
surrounds the intersection.
"This job has the largest landscaping package included
in the work," said Snehal Shah, the project engineer
in charge at NYDOT. "This is a very, very dense tree
area. Everything you see from the sky is green."
Not just green, but blue. General contractor Perini Corp.
is dredging Alley Pond, a 1.8-acre body of water nestled in
the interchange's southeastern corner. Perrini will also submerge
an oil separator unit to help prevent hazardous automobile
byproducts from draining into Little Neck Bay. The work should
be completed by October.
|