Integration Challenges
FIT Brings Together Old
and New
by Amy S. Choi
The old and the new don't always mix - unless they have to.
And they do - quite successfully - in the expansion and redevelopment
of the campus of the Fashion Institute of Technology, a college
of the State University of New York, located between 27th
and 28th streets and Seventh and Eighth avenues in Manhattan's
garment and fashion district.
The school originally opened in 1956, and its last construction
project was completed in 1975. As the student body grew, FIT
administrators knew by 1994 that they were facing a 258,000-sq.-ft.
space shortfall and two underutilized courtyards.
With the cost to acquire land and properties prohibitive in
Manhattan, the college hired Kevin Hom + Andrew Goldman Architects
P.C., specialists in designing educational facilities, to
master plan new additions to the cramped campus.
Designing for a Design Campus
"Here's a campus that has to compete with the city around
it," said Andrew Goldman, the firm's vice president.
"We needed to locate and provide campus amenities that
didn't exist before and create grand spaces but not make them
feel totally alien to the existing strong campus buildings
that are here."
The architects were careful to integrate the new developments
aesthetically with the existing facilities, but they still
wanted to punch it up a bit. For both the interior and exterior
of the new spaces, Hom + Goldman used ground-face block, an
upscale concrete block that has the polish of terrazzo.
The ground-face block is the same color as the original limestone
wrapping on the campus, so "architecturally the space
doesn't seem inappropriate in any way," Goldman said.
The architects did add a red and charcoal stripe to the exterior
to provide a "special luster," he added.
"Over the years, there were additions but there wasn't
an attempt to unify the campus," said Goldman. "We're
making the new additions destinations but want them aesthetically
to enter into the campus."
With that in mind, Hom + Goldman completed a master plan,
which was submitted to the Dormitory Authority of the State
of New York. DASNY, a state agency, helps manage the construction
and arranged the financing.
Overall, the 10-year, two-phase development plan will cost
$150 million and add 300,000 sq. ft. of new space, including
a great hall, exhibition space, conference center and dining
hall. In addition, 400,000 sq. ft. of space will be renovated
and a campus mall created.
Phase one of the plan, the addition of two buildings on two
underutilized sunken courtyards on the north side of the campus
and the creation of a pedestrian walkway, will just exceed
$50 million. The two courtyards stretch along 28th Street
side of the campus.
The approximately $20 million for the two new buildings, which
broke ground in August of last year, have been financed with
50 percent coming from the state of New York, 25 percent from
New York City and 25 percent from private capital.
Phase two of the master plan is currently in the development
stage.
Tight Spaces and Missing Blueprints
"One challenge of a site like this is that you are surrounded
by buildings and don't have clear access to it," said
Hans Gesell, a project manager at Wayman C. Wing Consulting
Engineers, the development's structural engineer. "(The
project) could have been practically impossible, but wasn't."
Harvey Spector, vice president of finance and operations at
FIT, said construction had to take place while 10,000 students
attended classes. "FIT is in use six days a week, so
managing the noise, the dust, controlling the access is difficult,"
he added. "The surprise is that it's gone so smoothly."
Nine months into the construction, the development team at
FIT had a couple of headaches pop up. For example, in order
not to disturb the foundation of the surrounding buildings,
engineers had to delve deep into bedrock. Because of the height
of the water table in New York City, they had to go through
a dewatering process, all of which was expected.
The contractors were surprised, however, to find that blueprints
that offered structural elements of the older buildings either
no longer existed or were not completely accurate. Surprises
included 6-in. variants in the floor slabs, a challenge for
developments that have three of four sides touching existing
buildings.
"I had connected some major new roofbeams to a column
that turned out not to be there (in the West Courtyard),"
Gesell said. "The column stopped, skipped one floor and
started at the next. So we supplied the missing column ourselves."
While installing a new elevator pit in the East Courtyard,
the construction team hit a foundation 2 ft. higher than Gesell
had expected it to be. So, the team chopped out some of the
foundation. Additionally, some of the limestone panels on
the existing structures were not supported satisfactorily.
"In every project we have a change-order contingency,"
said George Jefremow, project manager at URS Corp., the project's
construction manager. "Some unexpected things have occurred,
but we're still within our contingency limit."
Teamwork
The surprises would have been much more difficult for a team
that was less skilled at working together.
New York State's Wicks Law requires that public projects of
this size have a minimum of four contractors. "There
are five contractors, which should have made it a horror show,"
Goldman said. "But the nature of the team is great, and
they've been tremendously flexible. URS has been amazing as
a construction manager holding them together - it really is
a testament to George (Jeffremow)."
Jefremow said coordinating the five contractors was the toughest
aspect of the project. "(Under Wicks) URS is in essence
made into a GC without the power of holding the contracts,"
he added. "So our biggest challenge was initiating and
maintaining cooperation between the primes."
Very specific supplemental general agreements and coordination
drawings helped the process. "It works out 90 percent
of the time," said Jefremow, who has previously completed
two other DASNY projects.
"Hans (Gesell) goes to the site whenever he's called
and is a very flexible engineer," Goldman said. "He's
very creative and will work with you. They're not all that
way."
Gesell said that on every job, "you start seeing shadows
everywhere and worry that it's never going to come to a happy
conclusion. But I actually enjoyed visiting this site."
The Next Step
The two new buildings of phase one should be complete by February,
at which point the college hopes to get started on the 27th
Street Streetscape, which will create a pedestrian walkway.
The streetscape, however, is facing its own set of troubles.
Some neighbors on the block where the college owns and operates
eight buildings and rents space in several others are not
happy with the plan, said FIT's Spector. The plan is currently
in the approval process with various city agencies, but the
neighbors are suing the college to prevent the development.
Integrating the college's needs with those of the surrounding
community remains a problem for the project, but builders
and educators are optimistic.
"This is one of the better projects I've ever been on,"
Jefremow said. "The students are enthusiastic and appreciative,
the FIT staff has been more help than I could have believed
and I have good contractors. Sometimes people say city and
state agencies are impediments, but DASNY has been a fabulous
client to work for."
|