Lycee
Francais Unifies Under One Roof
By Jason Feldman
Carving a space for the Lycee Francais de New York proved
more difficult than obtaining truffles for a dollar.
It began as a simple desire of the 1,000-student K-12 private
school to house all of its students under one roof in a modern
building and provide them with a gym, cafeteria and auditorium.
Currently spread out in six separate buildings, the Lycee
Francais decided to build a new facility five years ago, said
Ada Hogan, assistant director of development for Lycee Francais
de New York.
In December 2000, the Lycee brought in Albanese Development
Corp., the project's Garden City, N.Y.-based developer, to
build a new 136,000-sq.-ft. facility, a block-through from
75th to 76th streets between York Avenue and the FDR Drive.
Getting Started
Construction on the project began in February 2002, and the
building will begin to be occupied by September with phased
move-ins starting in July. Getting it completed so quickly
meant a tight schedule.
In order to get a running start on the project, F.J. Sciame
Construction Co. Inc., the project's New York-based construction
manager, let out early bid packages for the foundation and
superstructure, said Marc Heiman, vice president and project
manager of the company.
"It had an enormous benefit [the early bid packages].
It was almost design-build," because some construction
documents were not completed before the bids were let out,
Heiman added.
However, the progress was slowed by the excavation, which
had to cut through 30 ft. of Manhattan's famous bedrock.
"Just the rock removal was difficult," said Kara
Olen, project engineer for Langan Engineering and Environmental
Services, the project's New York-based geotechnical engineer.
"The bottom elevation is 12 ft. below the river elevation
so there was water infiltration where we expected."
The excavation also ran up against the foundations of the
surrounding buildings.
"One building had a rubble foundation so we were concerned
about that," Olen said. "We did some structural
stabilization by bolting the rock below and strapping supports
into the floor slabs."
In addition, the Lycee's foundation, which consists of a
spread and stripped footing bearing on the rock and subgrade,
had to bear the load from the surrounding buildings. "The
building is squeezed by the surrounding buildings and the
foundation walls had to be designed to withstand the foundations,"
said Yefiam Gurevich, project manager for The Cantor Seinuk
Group, the project's New York-based structural engineer.
Gurevich said that an intricate system of drainage, pumps
and waterproofing was built to remove the water table and
water from the side of the building.
Making Time
Given all that, the excavation and foundation took longer
than expected, Heiman said. To make up for lost time, Sciame
reanalyzed the critical path and reshuffled some of the trades
and resequenced them.
"This job was originally a tight schedule to begin with
and we had to find the most cost-effective way to make up
time other than overtime," Heiman added. Minor spot overtime
was used as well as premiums to accelerate certain items.
The excavation paved the way for two gymnasiums and an auditorium
to be built below ground, which meant challenges regarding
column-free spaces. To create the large open space, massive
concrete girders were cast-in-place 30 ft. above the floor
to carry the load of the building over the below-grade spaces.
"The girders are about 65 to 70 ft. long by 4 ft. wide
by 8 ft. deep," Gurevich said. "You don't see those
kinds of girders, even on higher buildings." He added
that it is unusual that they would be built out of structural
concrete.
Rising from the base will be a concrete column and slab frame
for the two towers. Gurevich said the average span between
the columns was 23 ft. and the floor slab thickness averaged
9 in. Except on the first floor, where the slab will be 12
in., Heiman said the first-floor thickness was built to support
vehicular traffic because there will be a driveway through
the building that will enable buses to drop off and pick up
students.
Pouring the first-floor slab and the concrete girders took
six weeks, Heiman said. "We weren't on a two-day cycle,
but as we passed the first-floor slab, we were on a two- to
three-day cycle," said Jack Becker, executive vice president
of Albanese Development Corp.
The construction team also had to deal with an existing private
school across the street on 75th Street and a Consolidated
Edison facility at 75th and the FDR. To ensure the safety
of the children, flagmen were posted near the school, and
the crane had to be placed in the middle of the building to
allow unimpeded access to the ConEd facility, said Heiman.
European Touches
Enclosing the building will be a new material that has been
used in Europe for more than 40 years but is only now being
used in the United States. A channel glass system will be
used on the north tower to maximize daylight.
"It was selected because it is a beautiful material,"
said Susie Rodriguez, partner and partner-in-charge on the
project for Polshek Partnership Architects, the project's
New York-based architect. "There is a large white brick
building on 76th Street that acts as a light scoop and reflects
light back into the (new) building."
Another benefit of the channel glass is that it is a recycled
material. It also provided a clear span from slab to slab
rather than being interrupted, Rodriguez said.
Still, the glass had to undergo extensive testing to ensure
structural stability.
Classrooms have been placed on the perimeter of both towers
to maximize natural light.
Other architectural flourishes include the use of precast
on the south façade to make connections to the historic
limestone buildings and a central courtyard that will be placed
on the roof of the second floor. Hogan said that some classrooms
would open to the courtyard, which will allow freedom for
the children.
Classrooms will have a coloring scheme that reflects the
ages of the children, Hogan said. For the kindergarten through
fifth grade, which will be housed in the north tower, pastels
will be used.
In the south tower, home to the middle school and the high
school, more subdued tones will be used.
French doors will be installed to highlight the school's
French heritage.
|