|
Carrying the Load
New Luxury High-Rise Straddles Subway
by Adam Macy
900 Eighth Avenue, the Moinian Group's new 42-story residential
tower, will span a full block on the east side of Eighth Avenue
from 53rd to 54th streets.
At the edge of the theater district, near restaurant row
and the reinvigorated Columbus Circle where the new AOL Time
Warner headquarters is rising, the tower will feature 393
luxury rental apartments, a 550-car garage (replacing the
city-owned garage that had occupied the space) and flying
buttresses top and bottom.
The street level will feature 10,000 sq. ft. of commercial
space. The building, which is scheduled for completion in
September 2004, will comprise about 430,000 sq. ft. overall.
Hard construction costs - brick and mortar expenses - are
expected to run about $63 million.
From the Ground Down
In creating the concrete tower, workers first had to deal
with the ground underneath because a subway train rumbles
under the lot roughly every minute.
Two subway tunnels - one for the IRT's Nos. 2 and 3 trains
and the other for the IND's B and D trains - bisect under
the lot, running from the southeast corner at Eighth Avenue
and 53rd Street to the northwest corner at 54th Street. The
two tunnels lie at different levels below the site. One tunnel
is cored into the bedrock, while the rock was cut out for
the other tunnel.
"No load is permitted above the subway walls or roof
and we could not allow the load to spread through the rock,"
said Jacob Grossman, structural engineer on the job and president
of Rosenwasser-Grossman Consulting Engineers PC.
The solution was to build a series of major transfer beams
to shift the load toward the outer edge of the building. While
the transfer beams could have been made of steel or concrete,
concrete better served the complex needs of the project, which
included not only shifting the load to the outer edge, but
also dealing with the varying column layouts required for
the garage and residential portions.
"Concrete allows for more flexibility, and on this job
the concrete transfer beams are shaped to match the changing
height and space," Grossman explained.
Ninety caissons were drilled more than 50 ft. down and a
foundation and superstructure girder system of heavily reinforced
concrete was built over the tunnels to support the structure
above. Heavy 12- to 16-in. structural arches across the subway's
easement take the load of the garage and its four hydraulic
elevators. The building's 1,520-sq.-ft. cellar level bridges
the B and D line.
In addition, the tower's elevator shaft is cantilevered over
the subway tunnels because of the preferred location for the
residential levels, which forced the transfer of large gravity
and wind loads over several building levels.
"It's one of the most complex jobs we've done and we've
done close to a thousand concrete buildings in the city,"
Grossman added.
Tony Rafaniello, the onsite superintendent for HRH Construction
LLC, said the building is "not just slab on grade, slab
over tunnels."
He stressed the importance of the reinforced concrete girder/caisson
system and added that while slab on grade has no structural
value, the arches - which could be on grade or higher up -
have reinforcement that make them self-supportive.
"This project is atypical of most concrete jobs,"
said Frank Ross Jr., project executive for HRH Construction.
"To span the subway, build a 42-story building on top
and have no load imposed on the tunnels is a pretty amazing
feat."
From the Ground Up
The garage will be in the five-story, naturally ventilated
pedestal upon which the tower will extend. It will be clad
in architectural precast, poured-in-place concrete designed
to look like limestone.
The 37-story residential tower will feature floor-to-ceiling
windows and light-colored brick panels, culminating in a 50
ft. bulkhead. Other aesthetic niceties include the flying
buttresses, at the seventh floor and at the top, made of precast
concrete beams stretching up to 20 ft. from one corner to
another.
In the planning since 1997, 900 Eighth Avenue was redesigned
three times, said Moinian's project manager, Maria Rosenfeld.
Initial designs called for a taller, 52-floor building. "That
was too expensive to build. This is a simplified version,"
she said.
The project was financed under the "80/20" program,
through which a low-interest mortgage is guaranteed by the
New York State Housing Finance Agency. It also comes with
some long-term tax abatements. In return, Moinian agreed to
set aside one-fifth of the units for low- and moderate-income
tenants.
Market rate rents will be between $40 to $50 per sq. ft.,
Rosenfeld said. Studio apartments will be about 500 sq. ft.,
and one-bedrooms between 650 and 700 sq. ft. Two-bedroom units
could be as large as 1,200 sq. ft.
At the end of March, workers were completing the second-floor
slab and the third-floor frame, about three weeks away from
a hoped-for "two-day cycle."
Click here
for past Features >>
|